Air Mozilla/Weekly-Status-Reports/2012-04-11

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: April 11, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Richard Milewski
PROJECT WIKI: Air_Mozilla
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
2011-12-22 2011-12-22 R1 2012-04-16 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Theme Dev Complete
  • QA/Sec/Design Review
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
R2 Identify Systems / Scope TBD -- -- On Hold
R2 Final Design TS TBD --- On Hold
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
Digital Asset Manager Use/Not Use For R2 RM high -- --
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Acutal
Completion
Date
Bugzilla Status
Design
   R2 Design Approved TS 3/12 On Hold
   R2 PSD Delivered TS 3/16 On Hold
WebDev
   R1 Coding CC 3/26 - 4/6 4/10 Complete
   R1 Design Review TS/CC 4/2 - 4/6 4/10 - 4/11
   R1 Live CC 4/16
Content
   R1 Content Entry RM 4/16
Privacy
   R1 Review Stacy N/A
QA
   R1 Review RB 4/9 - 4/10 735459 In Progress
Security
   R1 Review YB 4/10 - 4/12 735454
IT
   R1 Launch Plan BS/CC 4/06 Complete