DOC VERSION: 1.0 | STATUS REPORT AS OF: March 20 2012 |
AUTHOR: Benjamin Sternthal |
TPM: Benjamin Sternthal |
PROJECT SPONSOR: David Ascher |
PROJECT WIKI: Betafarm |
Status
1. STATUS | |||||
Status Item | On Track | Caution | Crisis | N/A | Comment |
OVERALL STATUS | X | ||||
Schedule | X | ||||
Scope | X | ||||
Budget | X |
Schedule & Budget
2. SCHEDULE | |||
Start Date | Completion Date | ||
Original | Current | Original | Current |
Jan 17 | Jan 17 | March 30 | N/A |
3. BUDGET | |||
Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
N/A | N/A | N/A | N/A |
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
5. UPCOMING TASKS | ||||
Task | Owner | Due Date | Bugzilla | Comments |
Launch Plan | BB/PM/BS | 3/23 | --- | TBD |
Plan Blog Transition | Havi/BS | 3/20 | --- | TBD |
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
HP Design | DA | High | 2012-03-07 | 728410 | Complete | ||
Decide on Branding & Domain Name | DA | High | 2012-03-01 | -- | Complete |
Project Milestones
7. PROJECT MILESTONES | |||||||
Issue | Owner | Target Completion Date |
Revised Completion Date |
Actual Completion Date |
Bugzilla | Status | |
WebDev | |||||||
Release 1 Ready To Test | PM/Jfong | 3/23 | |||||
Release 1 Live | PM/Jfong | 4/6 | |||||
Content | |||||||
Blog Import | PM/HH | 3/16 | |||||
Blog Cleanup | HH | 3/19 - 3/23 | |||||
Privacy | |||||||
Data Safety Review | AH | 3/15 | 3/25 | 728334 | In Progress | ||
Privacy/Legal Review | Jishnu | 3/19 - 3/23 | 3/19 | Complete | |||
QA | |||||||
QA Review | RB | 3/26 - 3/30 | 728464 | ||||
Security | |||||||
Security Review | MG | 3/26 - 3/28 | 718891 | ||||
IT | |||||||
Setup Dev | BB | 3/7 | 733143 | In Progress | |||
Setup Staging | BB | 3/9 | 735773 | In progress | |||
Production Plan | BB/BS/PM | 3/23 |