DOC VERSION: 1.0 STATUS REPORT AS OF: March 20 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: David Ascher
PROJECT WIKI: Betafarm
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 17 Jan 17 March 30 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Legal/Privacy Review Complete
  • Data Safety Consultation Complete
  • Blog Transition Planning Meeting 3/20
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Launch Plan BB/PM/BS 3/23 --- TBD
Plan Blog Transition Havi/BS 3/20 --- TBD
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
HP Design DA High 2012-03-07 728410 Complete
Decide on Branding & Domain Name DA High 2012-03-01 -- Complete
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
WebDev
  Release 1 Ready To Test PM/Jfong 3/23
  Release 1 Live PM/Jfong 4/6
Content
   Blog Import PM/HH 3/16
   Blog Cleanup HH 3/19 - 3/23
Privacy
   Data Safety Review AH 3/15 3/25 728334 In Progress
   Privacy/Legal Review Jishnu 3/19 - 3/23 3/19 Complete
QA
   QA Review RB 3/26 - 3/30 728464
Security
   Security Review MG 3/26 - 3/28 718891
IT
   Setup Dev BB 3/7 733143 In Progress
   Setup Staging BB 3/9 735773 In progress
   Production Plan BB/BS/PM 3/23