Betafarm/Weekly-Status-Reports/2012-04-10
< Betafarm
Summary
| DOC VERSION: 1.0 | STATUS REPORT AS OF: April 10 2012 |
| AUTHOR: Benjamin Sternthal |
| TPM: Benjamin Sternthal |
| PROJECT SPONSOR: David Ascher |
| PROJECT WIKI: Betafarm |
Status
| 1. STATUS | |||||
| Status Item | On Track | Caution | Crisis | N/A | Comment |
| OVERALL STATUS | X | ||||
| Schedule | X | ||||
| Scope | X | ||||
| Budget | X | ||||
Schedule & Budget
| 2. SCHEDULE | |||
| Start Date | Completion Date | ||
| Original | Current | Original | Current |
| Jan 17 | Jan 17 | March 30 | April 16 |
| 3. BUDGET | |||
| Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
| N/A | N/A | N/A | N/A |
Recent Accomplishments
| 4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
| 5. UPCOMING TASKS | ||||
| Task | Owner | Due Date | Bugzilla | Comments |
| Launch! | BB/PM/BS | 4/16 | --- | |
Major Issues
| 6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
| Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
| -- | |||||||
Project Milestones
| 7. PROJECT MILESTONES | |||||||
| Issue | Owner | Target Completion Date |
Revised Completion Date |
Actual Completion Date |
Bugzilla | Status | |
| WebDev | |||||||
| Release 1 Ready To Test | PM/Jfong | 3/28 | 3/28 | Complete | |||
| Release 1 Live | PM/Jfong | 4/9 | 4/16 | ||||
| Content | |||||||
| Blog Import | BS/HH | 3/16 | 3/27 | 3/28 | Complete | ||
| Blog Cleanup | HH | 3/19 - 3/23 | 3/27- 3/30 | 4/3 | Complete(on-going) | ||
| Blog Live | HH | 4/4 | 4/4 | Complete | |||
| Site Content | DA/HH | 4/6 | |||||
| Privacy | |||||||
| Data Safety Review | AH | 3/15 | 3/25 | 728334 | Complete? | ||
| Privacy/Legal Review | Jishnu | 3/19 - 3/23 | 3/19 | Complete | |||
| QA | |||||||
| QA Review | RB | 3/28 - 4/3 | 728464 | In Progress | |||
| Security | |||||||
| Security Review | MG | 3/28 - 3/30 | 718891 | Complete | |||
| IT | |||||||
| Setup Dev | BB | 3/7 | 733143 | Complete | |||
| Setup Staging | BB | 3/9 | 735773 | Complete | |||
| Production Plan | BB/BS/PM | 3/23 | 3/27 | 4/3 | 744245 | Complete | |