Betafarm/Weekly-Status-Reports/2012-04-17

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: April 17 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: David Ascher
PROJECT WIKI: Betafarm
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 17 Jan 17 March 30 April 16
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Site Launched
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Launch! BB/PM/BS 4/16 --- Complete
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
--
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
WebDev
  Release 1 Ready To Test PM/Jfong 3/28 3/28 Complete
  Release 1 Live PM/Jfong 4/9 4/16 4/16 Complete
Content
   Blog Import BS/HH 3/16 3/27 3/28 Complete
   Blog Cleanup HH 3/19 - 3/23 3/27- 3/30 4/3 Complete
   Blog Live HH 4/4 4/4 Complete
   Site Content DA/HH 4/6
Privacy
   Data Safety Review AH 3/15 3/25 728334 Complete
   Privacy/Legal Review Jishnu 3/19 - 3/23 3/19 Complete
QA
   QA Review RB 3/28 - 4/3 728464 Complete
Security
   Security Review MG 3/28 - 3/30 718891 Complete
IT
   Setup Dev BB 3/7 733143 Complete
   Setup Staging BB 3/9 735773 Complete
   Production Plan BB/BS/PM 3/23 3/27 4/3 744245 Complete