Betafarm/Weekly-Status-Reports/2012-05-01

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: May 1 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: David Ascher
PROJECT WIKI: Betafarm
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
April 18 April 18 May 9 May 9
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • 1.1 QA Started
  • 1.2 Try for a short sprint, and finish project
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
--
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
--
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
WebDev
  Release 1.1 Ready To Test PM 5/1 Complete
  Release 1.1 Live PM/IT 5/9
Privacy
   Privacy Review N/A
QA
   QA Review RB 4/30 - 5/8 747223 In Progress
Security
   Security Review MG N/A
IT
   Prod Deployment BB 5/9