Agenda:
- Release schedule
- Code freeze (for blockers): Apr 30 (Delayed, new date: May 4)
- Registration server code complete: Apr 30 (Done)
- String Freeze: Apr 30 (Delayed, new date: May 4)
- H/W set up complete and configured: May 5
- Load testing done : May 13 (Delayed, new date: May 14)
- l10n complete: May 11
- Security reviews done: May 10
- RC release date: May 12
- QA release sign off: May 13
- Unit tests for Primary done: May 10
- Web content finalized and staged: May 13
- PR/Announcement complete and finalized: May 13
- GA date: May 17, 2010
- 1.3 release status update
- Production environment
- Load tests
- Client
- QA
- Metrics
- Marketing
- Support
- Ops Runbook
- iPhone client
- Other items
- History caps/backup
- Naming clients
- Custom home page if add-on installed (ala Fennec)
- Notes:
- Production environment is up and there's a problem. Gets a server incorrectly configured error.
- Can we test with hosts entries?
- 12 utest participants worldwide hitting the production servers now.
- Load test scripts aren't done. We really need to get it done today.
- utest will be using the systems until midnight, load tests will start tomorrow.
- Client is done with all blockers, just flushing out test coverage.
- QA hasn't found any blockers so far.
- We need to test migration.
- Large profiles - tchung will look into alternatives.
- Metrics is going to write a collector script and will switch over when we go live.
- AI: MConnor and I will talk about what else needs to be localized.
- AI: Need a blog post draft by the end of this week.
- Ops Runbook needs to be done.
- iPhone client internal beta is live.
- AI: Logging needs to be set up in production for security.
- Client security is done, notes coming soon.
- SLA: onsite backup every 2 days, offsite backup every week.
- AI: Ragavan will talk Mayumi/WebDev about changing/localizing the updated page.