Iteration #10 Status Report
Overall Project Performance
- From Iterations #1 - #10:
- Total Project Story Points: 1,003
- Story Points Completed: 547
- Story Points Remaining to Completion: 456
- Team Velocity: 57 Per Iteration
- Iterations Remaining to Completion: 9
- Forecasted Date to Completion of Development: November 25, 2013
- Total Stories Closed: 169
- Percentage of Work Completed: 55%
- Current Backlog Status:
- Story Backlog: 31 feature stories ready for development in upcoming iterations.
- Defect & Change Backlog: 56 defect and change stories ready for development in upcoming iterations.
- Planning Backlog: 9 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
Iteration #10 Performance
- Performance Highlights
- Team completed 75 story points across 30 features which resulted in an increased average team velocity of 57 story points per iteration.
- Average team velocity rate increased 11% from the previous iteration.
- Increase in average team velocity caused the Forecasted Date to Completion of Development to contract by 1 iteration to November 25.
- Point closure increased 47% from the previous iteration.
- Release Highlights
- At the conclusion of Iteration #10, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75,75, the Metro Team has a median velocity of 57 and there is a 90% likelihood that the actual velocity will fall between 32 and 75.
- Pessimistic Release Scenario - With a velocity performance of 32 development would be completed no earlier than 15 iterations on February 26, 2014.
- Expected Release Scenario - With a velocity performance of 57 development would be completed in 9 iterations on November 25, 2013.
- Optimistic Release Scenario - With a velocity performance of 75 development would be completed no later than 7 iterations on October 28, 2013.
- At the conclusion of Iteration #10, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75,75, the Metro Team has a median velocity of 57 and there is a 90% likelihood that the actual velocity will fall between 32 and 75.
- Quality Highlights
- The quality performance from the regression testing across Iterations #1 - #9 is as follows:
- 88% pass rate.
- 12% fail rate.
- 100% test coverage.
- The quality performance from the regression testing across Iterations #1 - #9 is as follows:
- Feature Completeness Highlights
- At the conclusion of Iteration #10, 44% of Feature Stories are Incomplete - development finished in a previous iteration but contain blocking defects and/or change requests.
- 14% of the current Defect & Change Backlog has yet to be related to a completed Feature Story.
31 Total; 0 Open (0%); 11 Resolved (35.48%); 20 Verified (64.52%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Iteration #9: View Backlog
- Points Completed: 51
- Stories Completed: 15
- Team Velocity: 51 Per Iteration
Iteration #10: View Backlog
- Points Completed: 75
- Stories Completed: 30
- Team Velocity: 57 Per Iteration
Upcoming Iteration
- Iteration #11: July 15, 2013 - July 26, 2013
- View Sprint Backlog