Iteration #12 Status Report
Overall Project Performance
- From Iterations #1 - #12:
- Total Project Story Points: 966
- Story Points Completed: 704
- Story Points Remaining to Completion: 262
- Team Velocity: 65 Per Iteration
- Iterations Remaining to Completion: 4
- Forecasted Date to Completion of Development: October 11, 2013
- Total Stories Closed: 232
- Percentage of Work Completed: 73%
Metro Preview Release
The Metro Preview Release is the en-US feature complete preview planned to be available on the Aurora channel during the Aurora 26 cycle.
- All feature stories, defects and changes required for the Metro Preview Release: View Backlog
- At the conclusion of Iteration #12, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75,75,77,80, the Metro Team has a median velocity of 65 and there is a 90% likelihood that the actual velocity will fall between 33 and 75.
- With a velocity performance of 65 the Metro Team can expect to complete between 132 and 300 more units of work with a median value of 262.
- With a forecasted total of 262 points remaining development would be completed in 4 iterations on October 11, 2013 - Development Iteration #16.
- The Metro Preview Release build is forecasted to "ride the trains" for Firefox 26
- Iteration #13 completed on mozilla-central August 26th, 2013.
- Iteration #14 completed on mozilla-central September 10th, 2013.
- Merge to Aurora 26 on September 16, 2013 during Iteration #15.
- Iterations #15 and #16 will be completed on mozilla-aurora, concluding all Preview Release work.
- A Windows Aurora Firefox build will be publicized as the Metro Preview Release.
- Iteration #17, still on Aurora, will be used to clean up any remaining carry-over and polish work.
- Merge to Beta at the conclusion of Iteration #17 on October 28, 2013, making Metro Firefox available to our Beta audience.
- Iterations #18 and #19 will be available if needed for responding to any critical Beta feedback issues that surface.
- Push to Release on December 10 with Firefox 26 at the conclusion of Iteration #20.
Iteration #12 Performance
- Performance Highlights
- Team completed 80 story points across 30 features which resulted in an increased average team velocity of 65 story points per iteration.
- Average team velocity rate increased 3% from the previous iteration.
- Point closure increased 6% from the previous iteration.
- Quality Highlights
- The quality performance from the regression testing across Iterations #1 - #11 is as follows:
- 94% pass rate - a 2% increase from the previous iteration.
- 6% fail rate - a 25% reduction from the previous iteration.
- 100% test coverage.
- The quality performance from the regression testing across Iterations #1 - #11 is as follows:
30 Total; 0 Open (0%); 19 Resolved (63.33%); 11 Verified (36.67%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Iteration #9: View Backlog
- Points Completed: 51
- Stories Completed: 15
- Team Velocity: 51 Per Iteration
Iteration #10: View Backlog
- Points Completed: 75
- Stories Completed: 30
- Team Velocity: 57 Per Iteration
Iteration #11: View Backlog
- Points Completed: 77
- Stories Completed: 34
- Team Velocity: 63 Per Iteration
Iteration #12: View Backlog
- Points Completed: 80
- Stories Completed: 30
- Team Velocity: 65 Per Iteration
Upcoming Iteration
- Iteration #13: August 13, 2013 - August 26, 2013
- View Sprint Backlog