- From Iterations #1 - #13:
- Total Project Story Points: 1,006
- Story Points Completed: 754
- Story Points Remaining to Completion: 252
- Team Velocity: 63 Per Iteration
- Iterations Remaining to Completion: 4
- Forecasted Date to Completion of Development: October 28, 2013
- Total Stories Closed: 258
- Percentage of Work Completed: 75%
Metro Preview Release
- All feature stories, defects and changes required for the Metro Preview Release: View Backlog
- At the conclusion of Iteration #13, given the historical velocity performance values of 30,32,33,46,50,51,63,68,74,75,75,77,80, the Metro Team has a median velocity of 63 and there is a 90% likelihood that the actual velocity will fall between 46 and 75.
- With a velocity performance of 63 the Metro Team can expect to complete between 184 and 300 more units of work with a median value of 252.
- With a forecasted total of 252 points remaining development would be completed in 4 iterations on October 28, 2013 - Development Iteration #17.
Iteration #13 Performance
- Performance Highlights
- Team completed 50 story points across 26 features which resulted in a decreased average team velocity of 63 story points per iteration.
- Average team velocity rate decreased 3% from the previous iteration.
- The decrease in average team velocity expanded the development complete forecast from Iteration #16 to Iteration #17 - October 28, 2013.
- Quality Highlights
- The quality performance from the regression testing across Iterations #1 - #11 is as follows:
- 95% pass rate - a 1% increase from the previous iteration.
- 5% fail rate - a 1% reduction from the previous iteration.
- 99% test coverage - a 1% reduction from the previous iteration.
- The quality performance from the regression testing across Iterations #1 - #11 is as follows:
26 Total; 0 Open (0%); 10 Resolved (38.46%); 16 Verified (61.54%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Iteration #9: View Backlog
- Points Completed: 51
- Stories Completed: 15
- Team Velocity: 51 Per Iteration
Iteration #10: View Backlog
- Points Completed: 75
- Stories Completed: 30
- Team Velocity: 57 Per Iteration
Iteration #11: View Backlog
- Points Completed: 77
- Stories Completed: 34
- Team Velocity: 63 Per Iteration
Iteration #12: View Backlog
- Points Completed: 80
- Stories Completed: 30
- Team Velocity: 65 Per Iteration
Iteration #13: View Backlog
- Points Completed: 50
- Stories Completed: 26
- Team Velocity: 63 Per Iteration