Firefox/Metro/Iteration14StatusReport

From MozillaWiki
< Firefox‎ | Metro
Jump to: navigation, search

Iteration #14 Status Report

Overall Project Performance

  • From Iterations #1 - #14:
    • Total Project Story Points: 968
    • Story Points Completed: 797
    • Story Points Remaining to Completion: 171
    • Team Velocity: 57 Per Iteration
    • Iterations Remaining to Completion: 3
    • Forecasted Date to Completion of Development: October 28, 2013
    • Total Stories Closed: 268
    • Percentage of Work Completed: 82%

Metro Preview Release

  • The Metro Preview Release (public name not finalized) is the en-US, and a robust batch of early locales (TBD), preview planned to be available on the Aurora channel during the Aurora 26 cycle.

  • The goal of the Metro Preview Release is to gather feedback and defects from the larger Aurora community.

  • Whether or not the Metro Preview Release will graduate from Aurora to Beta and Release channels is still to be determined. At a minimum, it should significantly increase the number of testers and feedback.

Metro V1 Public Release

  • At the conclusion of Iteration #14, given the historical velocity performance values of 30,32,33,43,46,50,51,63,68,74,75,75,77,80, the Metro Team has a median velocity of 57 and there is a 90% likelihood that the actual velocity will fall between 43 and 75.

  • With a velocity performance of 57 the Metro Team can expect to complete between 129 and 225 more units of work with a median value of 171.

  • With a forecasted total of 171 points remaining development would be completed in 3 iterations on October 28, 2013 - Development Iteration #17.

  • Forecasted development complete at Iteration #17 positions Metro for a Firefox 27 release on January 21, 2014.

Iteration #14 Performance

  • Performance Highlights
    • Team completed 43 story points across 10 features which resulted in a decreased average team velocity of 57 story points per iteration.
    • Average team velocity rate decreased 10% from the previous iteration.
    • The decrease in average team velocity over the two previous iterations did not impact the development complete forecast of Iteration #17 - October 28, 2013.

  • Quality Highlights
    • The quality performance from the regression testing across Iterations #1 - #13 is as follows:
      • 97% pass rate - a 2% increase from the previous iteration.
      • 3% fail rate - a 2% reduction from the previous iteration.
      • 48% test coverage - a 51% reduction from the previous iteration.

Full Query
ID Summary Priority Status
831944 [MP] Story - Open downloaded file from downloads app bar P2 VERIFIED
845152 [MP] Story - NewUI - Access and dismiss the new Firefox app bar P1 VERIFIED
882142 [MP] Defect - Manual or disabled updates from Metro needs cleanup P2 RESOLVED
893784 [MP] Defect - Metro update shutdown sometimes doesn't respawn Nightly after update P2 RESOLVED
893961 [MP] Defect - Clean up metro sync strings P2 RESOLVED
898477 [MP] Story - Initiate a file download and display the downloads app bar - Part IV P2 VERIFIED
903740 [MP] Defect - Clicking the overlay back button doesn't hide the tab strip P2 VERIFIED
907244 [MP] Defect - Opening a new tab when the page has focus doesn't correctly focus the location bar P2 VERIFIED
907410 [MP] Defect - Eliminate nested calls to ProcessEvents P1 RESOLVED
909019 [MP] Change - Clarify and simplify BrowserUI.newTab API P2 RESOLVED

10 Total; 0 Open (0%); 5 Resolved (50%); 5 Verified (50%);

Iteration Performance History

Iteration #1: View Backlog

  • Story Points Completed = 30
  • Stories Completed = 5
  • Team Velocity: 30 Per Iteration

Iteration #2: View Backlog

  • Story Points Completed = 32
  • Stories Completed = 6
  • Team Velocity: 32 Per Iteration

Iteration #3: View Backlog

  • Story Points Completed = 33
  • Stories Completed = 10
  • Team Velocity: 32 Per Iteration

Iteration #4: View Backlog

  • Story Points Completed = 63
  • Stories Completed = 14
  • Team Velocity: 40 Per Iteration

Iteration #5: View Backlog

  • Story Points Completed = 75
  • Stories Completed = 25
  • Team Velocity: 47 Per Iteration

Iteration #6: View Backlog

  • Points Completed: 74
  • Stories Completed: 20
  • Team Velocity: 51 Per Iteration

Iteration #7: View Backlog

  • Points Completed: 68
  • Stories Completed: 23
  • Team Velocity: 54 Per Iteration

Iteration #8: View Backlog

  • Points Completed: 46
  • Stories Completed: 21
  • Team Velocity: 53 Per Iteration

Iteration #9: View Backlog

  • Points Completed: 51
  • Stories Completed: 15
  • Team Velocity: 51 Per Iteration

Iteration #10: View Backlog

  • Points Completed: 75
  • Stories Completed: 30
  • Team Velocity: 57 Per Iteration

Iteration #11: View Backlog

  • Points Completed: 77
  • Stories Completed: 34
  • Team Velocity: 63 Per Iteration

Iteration #12: View Backlog

  • Points Completed: 80
  • Stories Completed: 30
  • Team Velocity: 65 Per Iteration

Iteration #13: View Backlog

  • Points Completed: 50
  • Stories Completed: 26
  • Team Velocity: 63 Per Iteration

Iteration #14: View Backlog

  • Points Completed: 43
  • Stories Completed: 10
  • Team Velocity: 57 Per Iteration

Upcoming Iteration