Iteration #14 Status Report
Overall Project Performance
- From Iterations #1 - #14:
- Total Project Story Points: 968
- Story Points Completed: 797
- Story Points Remaining to Completion: 171
- Team Velocity: 57 Per Iteration
- Iterations Remaining to Completion: 3
- Forecasted Date to Completion of Development: October 28, 2013
- Total Stories Closed: 268
- Percentage of Work Completed: 82%
Metro Preview Release
- The Metro Preview Release (public name not finalized) is the en-US, and a robust batch of early locales (TBD), preview planned to be available on the Aurora channel during the Aurora 26 cycle.
- The goal of the Metro Preview Release is to gather feedback and defects from the larger Aurora community.
- Whether or not the Metro Preview Release will graduate from Aurora to Beta and Release channels is still to be determined. At a minimum, it should significantly increase the number of testers and feedback.
Metro V1 Public Release
- At the conclusion of Iteration #14, given the historical velocity performance values of 30,32,33,43,46,50,51,63,68,74,75,75,77,80, the Metro Team has a median velocity of 57 and there is a 90% likelihood that the actual velocity will fall between 43 and 75.
- With a velocity performance of 57 the Metro Team can expect to complete between 129 and 225 more units of work with a median value of 171.
- With a forecasted total of 171 points remaining development would be completed in 3 iterations on October 28, 2013 - Development Iteration #17.
- Forecasted development complete at Iteration #17 positions Metro for a Firefox 27 release on January 21, 2014.
Iteration #14 Performance
- Performance Highlights
- Team completed 43 story points across 10 features which resulted in a decreased average team velocity of 57 story points per iteration.
- Average team velocity rate decreased 10% from the previous iteration.
- The decrease in average team velocity over the two previous iterations did not impact the development complete forecast of Iteration #17 - October 28, 2013.
- Quality Highlights
- The quality performance from the regression testing across Iterations #1 - #13 is as follows:
- 97% pass rate - a 2% increase from the previous iteration.
- 3% fail rate - a 2% reduction from the previous iteration.
- 48% test coverage - a 51% reduction from the previous iteration.
- The quality performance from the regression testing across Iterations #1 - #13 is as follows:
10 Total; 0 Open (0%); 5 Resolved (50%); 5 Verified (50%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Iteration #9: View Backlog
- Points Completed: 51
- Stories Completed: 15
- Team Velocity: 51 Per Iteration
Iteration #10: View Backlog
- Points Completed: 75
- Stories Completed: 30
- Team Velocity: 57 Per Iteration
Iteration #11: View Backlog
- Points Completed: 77
- Stories Completed: 34
- Team Velocity: 63 Per Iteration
Iteration #12: View Backlog
- Points Completed: 80
- Stories Completed: 30
- Team Velocity: 65 Per Iteration
Iteration #13: View Backlog
- Points Completed: 50
- Stories Completed: 26
- Team Velocity: 63 Per Iteration
Iteration #14: View Backlog
- Points Completed: 43
- Stories Completed: 10
- Team Velocity: 57 Per Iteration
Upcoming Iteration
- Iteration #15: Wed 9/11/13 - Tue 9/24/13
- View Sprint Backlog