Iteration #19 Status Report
Overall Project Performance
At the conclusion of Development Iteration #19:
- Total Project Story Points: 1,097
- Story Points Completed: 1,028
- Story Points Remaining to Development Completion: 69
- Team Velocity: 51 Per Iteration
- Iterations Remaining to Development Completion: 1
- Forecasted Date to Completion of Development: December 06, 2013
- Forecasted Release Version: Firefox 28 release on March 18, 2014. (View Release Calendar)
- Percentage of Points Completed: 94%
Metro V1 Public Release
- At the conclusion of Iteration #19, given the historical velocity performance values of 18,30,32,33,42,43,46,47,50,51,59,63,64,68,74,74,75,77,80, the Metro Team has a median velocity of 51 and there is a 90% likelihood that the actual velocity will fall between 43 and 68.
- With a velocity performance of 51 the Metro Team can expect to complete between 43 and 68 more units of work with a median value of 51.
- Given the velocity range of 43 - 68 story points and a forecasted total of 69 points remaining this iteration, there is a 90% likelihood that 1 - 26 story points worth of work will carry over into Aurora Iteration #21.
Iteration #19 Performance
- Performance Highlights
- Team completed 64 story points across 24 features which resulted in a team velocity of 51 story points per iteration.
- Team velocity increased by 1 point from the previous iteration.
24 Total; 0 Open (0%); 6 Resolved (25%); 18 Verified (75%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Iteration #9: View Backlog
- Points Completed: 51
- Stories Completed: 15
- Team Velocity: 51 Per Iteration
Iteration #10: View Backlog
- Points Completed: 75
- Stories Completed: 30
- Team Velocity: 57 Per Iteration
Iteration #11: View Backlog
- Points Completed: 77
- Stories Completed: 34
- Team Velocity: 63 Per Iteration
Iteration #12: View Backlog
- Points Completed: 80
- Stories Completed: 30
- Team Velocity: 65 Per Iteration
Iteration #13: View Backlog
- Points Completed: 50
- Stories Completed: 26
- Team Velocity: 63 Per Iteration
Iteration #14: View Backlog
- Points Completed: 43
- Stories Completed: 10
- Team Velocity: 57 Per Iteration
Iteration #15: View Backlog
- Points Completed: 47
- Stories Completed: 18
- Team Velocity: 51 Per Iteration
Iteration #16: View Backlog
- Points Completed: 42
- Stories Completed: 17
- Team Velocity: 50 Per Iteration
Iteration #17: View Backlog
- Points Completed: 19
- Stories Completed: 06
- Team Velocity: 50 Per Iteration
Iteration #18: View Backlog
- Points Completed: 59
- Stories Completed: 21
- Team Velocity: 50 Per Iteration
Iteration #19: View Backlog
- Points Completed: 64
- Stories Completed: 24
- Team Velocity: 51 Per Iteration
Upcoming Iteration
- Development Iteration #20 - View Backlog: Mon 11/25/13 - Fri 12/06/13