Overall Project Performance

  • From Iterations #1 - #3:
    • Total Points Completed: 95
    • Total Stories Closed: 21
    • Team Point Velocity: 32 per iteration
    • Average Story Closure Rate: 7 per iteration
    • Average Point Closure Rate: 33% per iteration
    • Scope Change (Defects and Changes): 39 points over 16 stories
  • Story Backlog: 58 stories ready for upcoming iterations.
  • Legacy Backlog: 3 stories remaining for QA testing.
  • On Hold Backlog: 13 stories remaining for Product Manager clarification before being moved into Story Backlog.
  • Planning Backlog: 0 stories for Team to review, relate to work items and assign point values.

Forecast Production Schedule

  • With the completion of Iteration #3 we have been able to develop an initial production forecast - the Expected Scenario.
  • The forecast is based only on data from the previous three iterations.
  • At the conclusion of each iteration, the production forecast will be updated to reflect the current state of the project.
  • At the conclusion of Iteration #6 there will be enough data to develop the Best Case and Worst Case development scenarios.
  • Current total project story points: 824
  • Project story points completed to date: 95
  • Current Team Velocity: 32
  • Forecasted number of story points remaining to complete the project: 729
  • Forecasted number of iterations remaining to complete the project: 24
  • Forecasted date for completion of development: May 14, 2014

Current Iteration Performance

  • Total value of iteration story points committed to: 69
  • Total value of iteration story points completed: 33
  • Completion Rate = 47%
  • Total number of iteration stories committed to: 14
  • Total number of iteration stories completed: 10
  • Completion Rate = 71%
  • Number of new Change Stories: 9 points over 3 stories
  • Number of new Defect Stories: 13 points over 6 stories
  • Iteration Velocity: 33

Iteration Performance History

Iteration #1
  • Iteration Points
    • Committed = 102
    • Completed = 30
    • Completion Rate = 29%
  • Iteration Stories
    • Committed = 13
    • Completed = 5
    • Completion Rate = 38%
  • Scope Change
    • New Defects Generated = 0
    • New Changes Generated = 3 points over 1 story
Iteration #2
  • Iteration Points
    • Committed = 110
    • Completed = 32
    • Completion Rate = 29%
  • Iteration Stories
    • Committed = 14
    • Completed = 6
    • Completion Rate = 42%
  • Scope Change
    • New Defects Generated = 4 points over 2 stories
    • New Changes Generated = 10 points over 4 stories