Iteration #5 Status Report
Overall Project Performance
- From Iterations #1 - #5:
- Total Project Story Points: 929
- Story Points Completed: 233
- Story Points Remaining to Completion: 696
- Team Velocity: 47 Per Iteration
- Iterations Remaining to Completion: 15
- Forecasted Date to Completion: December 23, 2013
- Total Stories Closed: 60
- Percentage of Work Completed: 26%
- Current Backlog Status:
- Story Backlog: 49 feature stories ready for development in upcoming iterations.
- Defect & Change Backlog: 34 defect and change stories ready for development in upcoming iterations.
- Planning Backlog: 7 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
- Triage Backlog: 11 stories for Team to review, relate work items to and assign point values.
Iteration #5 Performance
- Highlights
- Team completed 75 story points across 25 features - a 19% increase in performance from the previous iteration.
- Team has established a new average velocity rate of 47 story points per iteration - a 17% increase in performance from the previous iteration.
- Overall performance gain in story points and velocity has resulted in a new production forecast release of December 23, 2013 - a reduction of 3 iterations from the previous release update.
- Product Manager review of V1 Release List resulted in the removal of 9 Feature Stories to V2.
- At the conclusion of Iteration #6 the project will have acquired enough data to present three release forecast scenarios: Worst, Expected and Best case.
- Points Completed: 75
- Stories Completed: 25
- Team Velocity: 47 Per Iteration
25 Total; 0 Open (0%); 3 Resolved (12%); 22 Verified (88%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Upcoming Iteration
- Firefox Metro Iteration #6
- Iteration Backlog: View All Work
- Duration: April 17, 2013 - April 30, 2013
- Points: 110
- Stories: 30