Firefox/Metro/Iteration6StatusReport
From MozillaWiki
Contents
Iteration #6 Status Report
Overall Project Performance
- From Iterations #1 - #6:
- Total Project Story Points: 939
- Story Points Completed: 307
- Story Points Remaining to Completion: 632
- Team Velocity: 51 Per Iteration
- Iterations Remaining to Completion: 12
- Forecasted Date to Completion: November 19, 2013
- Total Stories Closed: 80
- Percentage of Work Completed: 35%
- Current Backlog Status:
- Story Backlog: 42 feature stories ready for development in upcoming iterations.
- Defect & Change Backlog: 41 defect and change stories ready for development in upcoming iterations.
- Planning Backlog: 11 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
- Triage Backlog: 13 stories for Team to review, relate work items to and assign point values.
Iteration #6 Performance
- Highlights
- Team completed 74 story points across 20 features which resulted in a new average velocity rate of 51 story points per iteration.
- Team increased its average velocity rate performance by 8% from the previous iteration.
- Team's overall performance gain has resulted in a new expected production release forecast of November 19, 2013 - a reduction of 2 iterations from the previous status update.
- Project has enough performance data to add Best Case and Worst Case scenarios to our release forecast.
- Best Case Release Forecast:
- If the team can achieve and maintain an average velocity of 71 points per iteration then development will be completed no later than October 02, 2013.
- Worst Case Release Forecast:
- If the team drops to an average velocity of 32 points per iteration then development will be completed no earlier than March 20, 2014.
- Product Manager revised the priority levels of the feature stories in the Story Backlog. The revision resulted in:
- 30 feature stories shifted to a P1 priority level.
- 1 feature story shifted to a P2 priority level.
- 10 feature stories shifted to a P3 priority level.
- 12 feature stories shifted to a P4 priority level.
- At the conclusion of Iteration #7 we will be releasing figures on the project's quality performance and defect levels.
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
22 Total; 0 Open (0%); 4 Resolved (18.18%); 18 Verified (81.82%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Upcoming Iteration
- Firefox Metro Iteration #7
- Iteration Backlog: View All Work
- Duration: May 02, 2013 - May 23, 2013
- Points: 124
- Stories: 23