Firefox/Metro/Iteration7StatusReport

From MozillaWiki
< Firefox‎ | Metro
Jump to: navigation, search

Iteration #7 Status Report

Overall Project Performance

  • From Iterations #1 - #7:
    • Total Project Story Points: 964
    • Story Points Completed: 375
    • Story Points Remaining to Completion: 589
    • Team Velocity: 54 Per Iteration
    • Iterations Remaining to Completion: 11
    • Forecasted Date to Completion: November 19, 2013
    • Total Stories Closed: 103
    • Percentage of Work Completed: 41%
  • Current Backlog Status:
    • Story Backlog: 33 feature stories ready for development in upcoming iterations.
    • Defect & Change Backlog: 35 defect and change stories ready for development in upcoming iterations.
    • Planning Backlog: 7 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
    • Triage Backlog: 3 stories for Team to review, relate work items to and assign point values.

Iteration #7 Performance

  • Highlights
    • Team completed 68 story points across 23 features which resulted in an increased average velocity rate of 54 story points per iteration.
    • Team increased its average velocity rate performance by 5% from the previous iteration.
    • The gain in average team velocity was not sufficient enough to impact our production release forecasts and therefore no dates have changed:
      • Pessimistic Release Scenario - The average velocity figure of the worst 3 iterations is 32. If the team drops to this velocity figure, then development would be completed no earlier than 18 iterations on March 20, 2014.
      • Optimistic Release Scenario - The average velocity figure of the best 3 iterations is 72. If this velocity figure can be achieved and maintained, then development would be completed no later than 8 iterations on October 02, 2013.
      • Expected Release Scenario - The average velocity figure from all the previous iterations is 54. If this velocity figure can be maintained, then development would be completed in 11 iterations on November 19, 2013.
    • Project's quality performance and defect levels across all iterations:
      • 87% average pass rate.
      • 13% average fail rate.
      • 73% test coverage.
    • The development team is now assisting QA with testing on the project review day to help increase our test coverage.
    • Other strategies such as setting up automated testing and test days are being organized with QA to also help increase our test coverage.
    • At the conclusion of Iteration #8 we will be releasing figures on the project's feature completeness levels.

No results.

0 Total; 0 Open (0%); 0 Resolved (0%); 0 Verified (0%);

Iteration Performance History

Iteration #1: View Backlog

  • Story Points Completed = 30
  • Stories Completed = 5
  • Team Velocity: 30 Per Iteration

Iteration #2: View Backlog

  • Story Points Completed = 32
  • Stories Completed = 6
  • Team Velocity: 32 Per Iteration

Iteration #3: View Backlog

  • Story Points Completed = 33
  • Stories Completed = 10
  • Team Velocity: 32 Per Iteration

Iteration #4: View Backlog

  • Story Points Completed = 63
  • Stories Completed = 14
  • Team Velocity: 40 Per Iteration

Iteration #5: View Backlog

  • Story Points Completed = 75
  • Stories Completed = 25
  • Team Velocity: 47 Per Iteration

Iteration #6: View Backlog

  • Points Completed: 74
  • Stories Completed: 20
  • Team Velocity: 51 Per Iteration

Iteration #7: View Backlog

  • Points Completed: 68
  • Stories Completed: 23
  • Team Velocity: 54 Per Iteration

Upcoming Iteration

  • Firefox Metro Iteration #8
    • Duration: May 28, 2013 - June 10, 2013
    • Points: 123
    • Stories: 21

No results.

0 Total; 0 Open (0%); 0 Resolved (0%); 0 Verified (0%);