Firefox/Metro/Iteration8StatusReport
From MozillaWiki
Contents
Iteration #8 Status Report
Overall Project Performance
- From Iterations #1 - #8:
- Total Project Story Points: 1000
- Story Points Completed: 421
- Story Points Remaining to Completion: 579
- Team Velocity: 53 Per Iteration
- Iterations Remaining to Completion: 11
- Forecasted Date to Completion of Development: November 19, 2013
- Total Stories Closed: 124
- Percentage of Work Completed: 44%
- Current Backlog Status:
- Story Backlog: 36 feature stories ready for development in upcoming iterations.
- Defect & Change Backlog: 54 defect and change stories ready for development in upcoming iterations.
- Planning Backlog: 7 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
- Triage Backlog: 9 stories for Team to review and assign to the Story Backlog or Defect/Change Backlog.
Iteration #8 Performance
- Performance Highlights
- Team completed 46 story points across 21 features which resulted in a decreased average team velocity rate of 53 story points per iteration.
- Average team velocity rate dropped 2% from the previous iteration.
- Despite this decline, the overall average team velocity has increased 11% from Iteration #1 - Iteration #8.
- Release Highlights
- The decrease in average team velocity was not sufficient enough to impact our production release forecasts and therefore no dates have changed:
- Pessimistic Release Scenario - The average team velocity figure of the worst 3 iterations is 32. If the team drops to this velocity figure, then development would be completed no earlier than 18 iterations on March 20, 2014.
- Optimistic Release Scenario - The average team velocity figure of the best 3 iterations is 72. If this velocity figure can be achieved and maintained, then development would be completed no later than 8 iterations on October 02, 2013.
- Expected Release Scenario - The average team velocity figure from all the previous iterations is 53. If this velocity figure can be maintained, then development would be completed in 11 iterations on November 19, 2013.
- The decrease in average team velocity was not sufficient enough to impact our production release forecasts and therefore no dates have changed:
- Quality Highlights
- At the conclusion of Iteration #8, the project's quality performance and defect levels across all iterations was:
- 89% average pass rate.
- 11% average fail rate.
- 95% test coverage.
- At the conclusion of Iteration #8, the project's quality performance and defect levels across all iterations was:
- Feature Completeness Highlights
- At the conclusion of Iteration #8, 34% of Feature Stories are Incomplete - development finished in a previous iteration but contain blocking defects and/or change requests.
- The above figure will increase as 33% of the current Defect & Change Backlog has yet to be related to a completed Feature Story.
21 Total; 0 Open (0%); 2 Resolved (9.52%); 19 Verified (90.48%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Upcoming Iteration
- Iteration #9: June 12, 2013 - June 25, 2013
- View Sprint Backlog