Firefox/Metro/Iteration9StatusReport

From MozillaWiki
< Firefox‎ | Metro
Jump to: navigation, search

Iteration #9 Status Report

Overall Project Performance

  • From Iterations #1 - #9:
    • Total Project Story Points: 1,032
    • Story Points Completed: 472
    • Story Points Remaining to Completion: 560
    • Team Velocity: 51 Per Iteration
    • Iterations Remaining to Completion: 11
    • Forecasted Date to Completion of Development: December 05, 2013
    • Total Stories Closed: 139
    • Percentage of Work Completed: 48%
  • Current Backlog Status:
    • Story Backlog: 32 feature stories ready for development in upcoming iterations.
    • Defect & Change Backlog: 58 defect and change stories ready for development in upcoming iterations.
    • Planning Backlog: 8 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
    • Triage Backlog: 7 stories for Team to review and assign to the Story Backlog or Defect/Change Backlog.

Iteration #9 Performance

  • Performance Highlights
    • Team completed 51 story points across 19 features which resulted in a decreased average team velocity of 51 story points per iteration.
    • Average team velocity rate dropped 4% from the previous iteration.
    • Decline in average team velocity caused the Forecasted Date to Completion of Development to increase by 1 iteration from November 19 to December 05.
    • Despite the decline in average team velocity, point closure increased 10% from the previous iteration.

  • Release Highlights
    • At the conclusion of Iteration #9, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75, the Metro Team has a median velocity of 51 and there is a 90% likelihood that the actual velocity will fall between 32 and 74.
      • Pessimistic Release Scenario - With a velocity performance of 32 development would be completed no earlier than 17 iterations on March 07, 2014.
      • Expected Release Scenario - With a velocity performance of 51 development would be completed in 11 iterations on December 06, 2013.
      • Optimistic Release Scenario - With a velocity performance of 74 development would be completed no later than 8 iterations on October 23, 2013.

  • Quality Highlights
    • The quality performance from the regression testing across Iterations #1 - #8 is as follows:
      • 90% pass rate.
      • 10% fail rate.
      • 88% test coverage.

  • Feature Completeness Highlights
    • At the conclusion of Iteration #9, 44% of Feature Stories are Incomplete - development finished in a previous iteration but contain blocking defects and/or change requests.
    • 14% of the current Defect & Change Backlog has yet to be related to a completed Feature Story.

Full Query
ID Summary Priority Status
811413 Story - Domain highlighting P3 VERIFIED
817820 Defect - Cursor should change to reflect that "middle-click scrolling" (autoscroll) is active P2 VERIFIED
826552 Defect - Add an indicator for the title (Bookmarks, History, Remote tabs) on start page P2 RESOLVED
831909 Story - Text selection in Firefox app bar (touch) P1 VERIFIED
837293 Story - Functioning non-English Keyboard P2 VERIFIED
849266 Story - APZC - Part I: Discovery and Prototyping P1 RESOLVED
860248 Defect - Tapping on content while selection is active clears the selection but leaves grippers behind P2 VERIFIED
877666 Defect - Validation sometimes enables for the nav bar P1 VERIFIED
877765 Defect - Findbar text edit is misaligned with findbar buttons P3 VERIFIED
879392 Change - Remove support for sending input to plugins P3 RESOLVED
879631 Change - Remove form navigation code P2 VERIFIED
880855 Defect - Back and Tab overlay buttons should be repositionable P2 VERIFIED
880986 Defect - No Reload Button P2 VERIFIED
881928 Defect - Tap-and-drag near edit box with monocles active causes selection highlighting to disappear but monocles remain P1 VERIFIED
882598 Defect - Rename updateAuto.label to reflect string change P1 VERIFIED

15 Total; 0 Open (0%); 3 Resolved (20%); 12 Verified (80%);

Iteration Performance History

Iteration #1: View Backlog

  • Story Points Completed = 30
  • Stories Completed = 5
  • Team Velocity: 30 Per Iteration

Iteration #2: View Backlog

  • Story Points Completed = 32
  • Stories Completed = 6
  • Team Velocity: 32 Per Iteration

Iteration #3: View Backlog

  • Story Points Completed = 33
  • Stories Completed = 10
  • Team Velocity: 32 Per Iteration

Iteration #4: View Backlog

  • Story Points Completed = 63
  • Stories Completed = 14
  • Team Velocity: 40 Per Iteration

Iteration #5: View Backlog

  • Story Points Completed = 75
  • Stories Completed = 25
  • Team Velocity: 47 Per Iteration

Iteration #6: View Backlog

  • Points Completed: 74
  • Stories Completed: 20
  • Team Velocity: 51 Per Iteration

Iteration #7: View Backlog

  • Points Completed: 68
  • Stories Completed: 23
  • Team Velocity: 54 Per Iteration

Iteration #8: View Backlog

  • Points Completed: 46
  • Stories Completed: 21
  • Team Velocity: 53 Per Iteration

Iteration #9: View Backlog

  • Points Completed: 51
  • Stories Completed: 15
  • Team Velocity: 51 Per Iteration

Upcoming Iteration