Firefox/Metro/Iteration9StatusReport
From MozillaWiki
Contents
Iteration #9 Status Report
Overall Project Performance
- From Iterations #1 - #9:
- Total Project Story Points: 1,032
- Story Points Completed: 472
- Story Points Remaining to Completion: 560
- Team Velocity: 51 Per Iteration
- Iterations Remaining to Completion: 11
- Forecasted Date to Completion of Development: December 05, 2013
- Total Stories Closed: 139
- Percentage of Work Completed: 48%
- Current Backlog Status:
- Story Backlog: 32 feature stories ready for development in upcoming iterations.
- Defect & Change Backlog: 58 defect and change stories ready for development in upcoming iterations.
- Planning Backlog: 8 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
- Triage Backlog: 7 stories for Team to review and assign to the Story Backlog or Defect/Change Backlog.
Iteration #9 Performance
- Performance Highlights
- Team completed 51 story points across 19 features which resulted in a decreased average team velocity of 51 story points per iteration.
- Average team velocity rate dropped 4% from the previous iteration.
- Decline in average team velocity caused the Forecasted Date to Completion of Development to increase by 1 iteration from November 19 to December 05.
- Despite the decline in average team velocity, point closure increased 10% from the previous iteration.
- Release Highlights
- At the conclusion of Iteration #9, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75, the Metro Team has a median velocity of 51 and there is a 90% likelihood that the actual velocity will fall between 32 and 74.
- Pessimistic Release Scenario - With a velocity performance of 32 development would be completed no earlier than 17 iterations on March 07, 2014.
- Expected Release Scenario - With a velocity performance of 51 development would be completed in 11 iterations on December 06, 2013.
- Optimistic Release Scenario - With a velocity performance of 74 development would be completed no later than 8 iterations on October 23, 2013.
- At the conclusion of Iteration #9, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75, the Metro Team has a median velocity of 51 and there is a 90% likelihood that the actual velocity will fall between 32 and 74.
- Quality Highlights
- The quality performance from the regression testing across Iterations #1 - #8 is as follows:
- 90% pass rate.
- 10% fail rate.
- 88% test coverage.
- The quality performance from the regression testing across Iterations #1 - #8 is as follows:
- Feature Completeness Highlights
- At the conclusion of Iteration #9, 44% of Feature Stories are Incomplete - development finished in a previous iteration but contain blocking defects and/or change requests.
- 14% of the current Defect & Change Backlog has yet to be related to a completed Feature Story.
15 Total; 0 Open (0%); 3 Resolved (20%); 12 Verified (80%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Iteration #9: View Backlog
- Points Completed: 51
- Stories Completed: 15
- Team Velocity: 51 Per Iteration
Upcoming Iteration
- Iteration #10: June 26, 2013 - July 11, 2013
- View Sprint Backlog