Start of project
- Name each of the following:
- Project sponsor: Jay Patel
- Main IT contact: mrz
- Metrics contact: Ken Kovash
- Main WebDev contact: N/A
- Main QA contact: Raymond Etornam
- Main Security contact: N/A
- Main third party contact (if developed externally): Craig Cook
- Final application owner/maintainer: Developer Marketing Team
- Outline the following:
- Overall goal of the project
- Improve organization of posts and discoverability by redesigning the Hacks blog.
- Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc)
- DB merge with production to retain configuration and content changes made on stage (if possible).
- Setup regular backups of all posts (if not done already)
- Initial timeline
- Design: Oct 15 - Nov 18
- Chris Howse's final design: http://moz.howsehold.org/hacks/
- Development: Nov 24 - Dec 21
- SVN: http://viewvc.svn.mozilla.org/vc/projects/hacks.mozilla.org/trunk/
- Craig Cook's test instance: http://mozilla.focalcurve.com/mozhacks/
- Staging: Dec 22 - Dec 28
- Initial update: https://bugzilla.mozilla.org/show_bug.cgi?id=536341)
- .htaccess fix: https://bugzilla.mozilla.org/show_bug.cgi?id=536508)
- Testing: Dec 28 - Dec 31
- Test Results: https://wiki.mozilla.org/MDN/Hacks/WebQAv1
- Launch: Jan 4?
- Design: Oct 15 - Nov 18
- Overall goal of the project
- External dependencies: None
- Dev environment specs
- WordPress 3.9 + standard env. requirements (already updated on stage, see https://bugzilla.mozilla.org/show_bug.cgi?id=536341)
- Does this project use any plugins or proprietary technology?
- WP Plugins: Co-Authors Plus, FC Pagination, Stats, TMH Pagehits, and ShareThis (already checked into SVN and tested on stage)
Staging Signoff [DONE]
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged: Checked in, but not sure if everything is tagged. (http://viewvc.svn.mozilla.org/vc/projects/hacks.mozilla.org/trunk/)
- Initial architecture review by IT and WebDev: Done
- Plugin/tech review by Evangelism: Done
- Security review must be in-process: N/A
- Site must be password protected: N/A
- Review timeline to go live: N/A
- Review any production requirements so IT can order any new hardware needed: N/A
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff
- Final Security signoff
- Final Metrics signoff
- Operations documents filled for support & any training complete
- Monitors in place