Status Report for Fennec - Tracking Protection - for the week of 29/06/15 - 07/07/15

Overall Project Health

This Week Last Week

YELLOW.jpg

N/A

Exec Summary/Hot Topics

  • Team selected 50% of the available work for the release for the first of three possible two week sprints, which was a fairly ambitious target
  • Presently at half way through the first sprint completed work sits at 5% of the total planned for the release, rather than the targeted 25% (half of the 50% commitment)
  • Status is yellow rather than red as it is likely the team will at least come close to catching up over the next week of the sprint, as another 19% of the available work is currently in review.


Risks & Issues

Description of Risk/Issue State Owner Plan to Resolve/Mitigation Target Date
Team assigned is not 100% dedicated to Tracking Protection work, which has potential to impact ability to complete work Open Margaret, Jenn Monitor how the team is doing in terms of meeting commitment for Tracking Protection, and discuss adjusting other workload as neccessary Ongoing for the release

Accomplished for the Last Period

  • First exercise in sizing and selection completed, and commitments made
  • Landed Bug 1175969
  • Patches for bugs 1173623 and 1175970 submitted for review

Planned for Last Period but Not Accomplished

  • Have not yet reached half of the point commitment for the sprint, at half way through the timeline

Planned for the Upcoming Period

  • Attempt to catch up on remaining work to meet the 21 point commitment for the sprint, including follow-up to close out items in review as necessary.