Status Report for Fennec - Tracking Protection - for the week of 29/06/15 - 07/07/15
Overall Project Health
This Week | Last Week |
---|---|
N/A |
Exec Summary/Hot Topics
- Team selected 50% of the available work for the release for the first of three possible two week sprints, which was a fairly ambitious target
- Presently at half way through the first sprint completed work sits at 5% of the total planned for the release, rather than the targeted 25% (half of the 50% commitment)
- Status is yellow rather than red as it is likely the team will at least come close to catching up over the next week of the sprint, as another 19% of the available work is currently in review.
Risks & Issues
Description of Risk/Issue | State | Owner | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|
Team assigned is not 100% dedicated to Tracking Protection work, which has potential to impact ability to complete work | Open | Margaret, Jenn | Monitor how the team is doing in terms of meeting commitment for Tracking Protection, and discuss adjusting other workload as neccessary | Ongoing for the release |
Accomplished for the Last Period
- First exercise in sizing and selection completed, and commitments made
- Landed Bug 1175969
- Patches for bugs 1173623 and 1175970 submitted for review
Planned for Last Period but Not Accomplished
- Have not yet reached half of the point commitment for the sprint, at half way through the timeline
Planned for the Upcoming Period
- Attempt to catch up on remaining work to meet the 21 point commitment for the sprint, including follow-up to close out items in review as necessary.
Important Links/References
- Work Tracking Spreadsheet
- Meta bug for Tracking Protection work