Connected Devices Weekly Update/2017-01-19: Difference between revisions

adding project Magnet update
m (add link)
(adding project Magnet update)
Line 28: Line 28:
! style="background:#00EC00;" | On Target
! style="background:#00EC00;" | On Target
|  
|  
* Bulleted list item
* Gate 1 passed last Friday Jan 13th ([https://docs.google.com/presentation/d/1oPxDE4A4qpA4UVlmn5q8pfRtyagFV-WfJ-JGPwABvNc/edit?usp=sharing Deck] and [https://vreplay.mozilla.com/replay/showRecordDetails.html?sortBy=date&viewCount=1&currentPage=1&groupBy=combo&roomFilter=&usernameFilter=&searchFilter=&usernameFullFilter=&myManager=-1&adminManager=0&webCast=0&command=&recId=4015&auxMessage=&auxMessage1=&lang=en&langChanged=&tenantFilter=&securityTab Video Recording])
* Bulleted list item
[[File:Magnet ProgramTimeline afterGate1.png|500px]]
 
'''Schedule'''
* UX Wireframes (first Iteration): 20/01/2017
* Visual Design of the app finished: 24/02/2017
* Street Art content included in the Metadata Server: March 31
* Beta version of the application ready in the stores: March 31
* Marketing campaign launched: during April 2017
 
'''Planning Tasks'''
* Many planning activities during this week. Meetings held and scheduled with marketing, legal, visual to plan Q1 work focused on the beta version of the app targeted for March 31st.
* Clarifying the Statement of Work for the Visual work and also for the content to be included in the London Street Art campaign
 
''' Team updates'''
* Liz is joining the team to help us with the content strategy
* Mihaela will also help us to plan a Usability Testing
 
'''Engineering Tasks'''
* [[Connected_Devices/Projects/Magnet/Sprint_10|Sprint 10]] (January 9th - January 20th) is finishing this week
** Backend: Static API to serve jsons for the list view and each story view, Dockerization for dev/test/prod environment
** Client/Frontend: Bootstrap new react-native app, API and development of some React Components (Magnetometer implementation for arrow direction, Location Services, Map View)
* Scheduled next Sprint Planning tomorrow so we will start working on it next week
|-
|-