* Status: '''Green''' - In Development. | * Status: '''Green''' - In Development. | ||
* Team is [https://mzl.la/ | * Team is [https://mzl.la/2GoDoCJ currently working on Iteration #4] which runs from May 14 - May 25. | ||
* A cumulative completion of | * A cumulative completion of 20 bugs is required by the conclusion of Iteration #4 to remain on schedule. | ||
* Team has, to date, a cumulative completion of 19 bugs for Iteration #4. | * Team has, to date, a cumulative completion of 19 bugs for Iteration #4. | ||
* Team has [https://mzl.la/2HyVqTB completed 66%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog]. | * Team has [https://mzl.la/2HyVqTB completed 66%] of the entire [https://mzl.la/2pe4jLM Milestone 1 - 3 Backlog]. | ||