Support/Fennec Project Plan: Difference between revisions

Jump to navigation Jump to search
Line 35: Line 35:
=Resource plan=
=Resource plan=
*Project lead: Laura
*Project lead: Laura
*Once we have delivered SUMO 1.1.1 (May 28), Eric can commence work on the critical path dev items.  This puts delivery into end of July.
*Once we have delivered SUMO 1.1.1 (May 28), Eric can commence work on the critical path dev items.  This puts delivery into August.
*Design work needs to be outsourced ASAP, John Slater to advise.
*Design work needs to be outsourced ASAP, John Slater to advise.
*Front end work to be done by Paul C, not heavy, should fit around his metric dashboard work.  May need additional supplementation from webdev (rdoherty?)
*Front end work to be done by Paul C, not heavy, should fit around his metric dashboard work.  May need additional supplementation from webdev (rdoherty?)
*SUMO team work to be done by Chris + Cheng
*SUMO team work to be done by Chris + Cheng
1,623