Mobile/Firefox for iOS/End Game Checklist: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
No edit summary
No edit summary
Line 7: Line 7:
|-
|-
| align="left"| Expand Test Flight Externally
| align="left"| Expand Test Flight Externally
|
|Karen, Jenn
|
|Done
|
|06/22
| align="left"|  
| align="left"| Email & invites sent 06/23.  Anyone who has not installed in a week (6/30) to be removed.


|-
|-
| align="left"| First Impressions survey distributed
| align="left"| First Impressions survey distributed
|
|Rob R
|
|Done
|
|6/24
| align="left"|  
| align="left"| Sent to first cohort of 60% who installed quickly.  Will be sent to remainder early next week


|-
|-
| align="left"| Initial NPS Score
| align="left"| Initial NPS Score
|
|Rob R
|
|Open
|
|6/30
| align="left"|  
| align="left"|  


|-
|-
| align="left"| Development Feature Complete
| align="left"| Development Feature Complete
|
|All Eng
|
|On going
|
|? 7/3 ?
| align="left"|  
| align="left"| Some debate on the definition of this.  Ignore if you like and move on to string freeze!


|-
|-
| align="left"| 'Media Preview' build
| align="left"| Second survey distributed
|
|
|
|
Line 41: Line 41:


|-
|-
| align="left"| Second survey distributed
| align="left"| Updated NPS Score
|
|
|
|
Line 48: Line 48:


|-
|-
| align="left"| Updated NPS Score
| align="left"| Finalize String copy (Matej)
|
|
|
|
Line 55: Line 55:


|-
|-
| align="left"| Finalize String copy (Matej)
| align="left"| Verifying all strings are localizable
|
|
|
|
Line 62: Line 62:


|-
|-
| align="left"| Verifying all strings are localizable
| align="left"| String Freeze for L10N - July 3rd
|
|
|
|
Line 69: Line 69:


|-
|-
| align="left"| String Freeze for L10N - July 3rd
| align="left"| 'Media Preview' build
|
|
|
|

Revision as of 17:33, 26 June 2015

Milestone/Deliverable Owner Status Target/Timeline Notes
Expand Test Flight Externally Karen, Jenn Done 06/22 Email & invites sent 06/23. Anyone who has not installed in a week (6/30) to be removed.
First Impressions survey distributed Rob R Done 6/24 Sent to first cohort of 60% who installed quickly. Will be sent to remainder early next week
Initial NPS Score Rob R Open 6/30
Development Feature Complete All Eng On going ? 7/3 ? Some debate on the definition of this. Ignore if you like and move on to string freeze!
Second survey distributed
Updated NPS Score
Finalize String copy (Matej)
Verifying all strings are localizable
String Freeze for L10N - July 3rd
'Media Preview' build
L10N complete/cut-off for release
Last uplift from L10N source into gh repo
Web Compatibility testing kicked off
Final EN Marketing copy for product landing page available - DONE
Final Marketing copy for store description available - Not Done
Copy for snippets/social (User Engagement)
Final EN Privacy Notice available from Legal (Geoff)
Final localized Privacy Notice available
Final SUMO articles published (Joni, Roland)
All Release Blockers Resolved/Verified
Confirm No privacy, security or legal blockers (revisit with Geoff, Marshall)
Confirm no Web Compatibility blockers Security code review? Do we need to engage someone external?
Pre-Final build available
Final Screen Shots for store available (Arcadio)
RC1 build available
RC1 build signed off by QA (incl. Min Sys and Crash requirements)
Test accounts provided to Apple for review
RC1 build uploaded to store
Backup - RC2 build available
Backup - RC2 build signed off by QA
Backup - RC2 build uploaded to store
Launched and available to download (Upload by +2 weeks)