===Onboarding Team=== | ===Onboarding Team=== | ||
* In Development. | * In Development. | ||
* | * Team is working on [https://docs.google.com/spreadsheets/d/171zU6dTHonlem-bTjyT-oDFXM6dBBHn2_pG2YdNpUGU/edit?usp=sharing Release III] (July 4 - August 14) with 23% of the release goal completed. | ||
* Team has [https://mzl.la/2so1BCW completed 53%] of the Project MVP Backlog. | |||
* On track for completion of the [https://mzl.la/2tGWwcL Project MVP Backlog] for Release 57. | |||
* QA has [https://mzl.la/2rmXYfN verified 100%] of all Project MVP Backlog work requiring testing. | |||
* [https://mzl.la/2so3v6u Project Reserve Backlog] contains 23 work items: 14 unassigned, 7 assigned and 2 completed. | |||
<p> </p> | <p> </p> | ||
===Preference Team=== | ===Preference Team=== | ||
Revision as of 03:15, 5 July 2017
Photon Project Status Updates
Tuesday July 4, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 60% of the release goal completed.
- Team has completed 59% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 36% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 16 work items: 12 unassigned, 1 assigned and 3 completed.
Performance Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 67% of the release goal completed.
- Team has completed 71% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 8% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 123 work items: 83 unassigned, 14 assigned and 26 completed.
Structure Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 82% of the release goal completed.
- Team has completed 65% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 47% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 32 work items: 22 unassigned, 1 assigned and 9 completed.
Animation Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 67% of the release goal completed.
- Team has completed 62% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 44% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 16 work items: 13 unassigned and 1 assigned and 2 completed.
Onboarding Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 23% of the release goal completed.
- Team has completed 53% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 100% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 23 work items: 14 unassigned, 7 assigned and 2 completed.
Preference Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 72% of the release goal completed.
- Team has completed 59% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 55% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 17 work items: 17 unassigned, 0 assigned and 0 completed.