Photon Project Status Updates

Tuesday August 22, 2017

Note: Updated every Tuesday.

Project Tracking

Visual Redesign Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 73% of the release goal completed.
  • Team has completed 99% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 75% of all Project MVP Backlog work requiring testing.
  • Team has completed 16 high priority reserve work items in the final release.

Performance Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 13% of the release goal completed.
  • Team has completed 92% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 45% of all Project MVP Backlog work requiring testing.
  • Team has no plans to complete high priority reserve work items in the final release.

Structure Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 40% of the release goal completed.
  • Team has completed 94% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 82% of all Project MVP Backlog work requiring testing.
  • Team has completed 8 high priority reserve work items in the final release.

Animation Team

  • MVP Completed.
  • Team has completed 100% of the Project MVP Backlog.
  • QA has verified 84% of all Project MVP Backlog work requiring testing.
  • Team has completed 7 high priority reserve work items in the final release.

Onboarding Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 55% of the release goal completed.
  • Team has completed 94% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 81% of all Project MVP Backlog work requiring testing.
  • Team has completed 5 high priority reserve work items in the final release.

Preference Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 68% of the release goal completed.
  • Team has completed 95% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 70% of all Project MVP Backlog work requiring testing.
  • Team has completed 0 high priority reserve work items in the final release.