| Line 20: | Line 20: | ||
* Team has [http://tinyurl.com/k3cmwj3 completed 73%] of the Project MVP Backlog. | * Team has [http://tinyurl.com/k3cmwj3 completed 73%] of the Project MVP Backlog. | ||
* On track for completion of the [http://tinyurl.com/l7lhk8h Project MVP Backlog] for Release 57. | * On track for completion of the [http://tinyurl.com/l7lhk8h Project MVP Backlog] for Release 57. | ||
* QA has [ | * QA has [https://mzl.la/2sQiOVI verified 10%] of all Project MVP Backlog work requiring testing. | ||
* [http://tinyurl.com/k3mcbl6 Project Reserve Backlog] contains 124 work items: 82 unassigned, 14 assigned and 28 completed. | * [http://tinyurl.com/k3mcbl6 Project Reserve Backlog] contains 124 work items: 82 unassigned, 14 assigned and 28 completed. | ||
<p> </p> | <p> </p> | ||
Revision as of 13:59, 13 July 2017
Photon Project Status Updates
Tuesday July 11, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 64% of the release goal completed.
- Team has completed 61% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 37% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 19 work items: 15 unassigned, 0 assigned and 4 completed.
Performance Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 73% of the release goal completed.
- Team has completed 73% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 10% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 124 work items: 82 unassigned, 14 assigned and 28 completed.
Structure Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 88% of the release goal completed.
- Team has completed 68% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 52% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 39 work items: 26 unassigned, 2 assigned and 11 completed.
Animation Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 78% of the release goal completed.
- Team has completed 74% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 45% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 17 work items: 13 unassigned and 2 assigned and 2 completed.
Onboarding Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 46% of the release goal completed.
- Team has completed 56% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 100% of all Project MVP Backlog work requiring testing.
Preference Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 77% of the release goal completed.
- Team has completed 63% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 59% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 16 work items: 15 unassigned, 1 assigned and 0 completed.