=Photon Project Status Updates= | =Photon Project Status Updates= | ||
<p> </p> | <p> </p> | ||
==Tuesday | ==Tuesday August 1, 2017== | ||
<sub>''Note: Updated every Tuesday.''</sub> | <sub>''Note: Updated every Tuesday.''</sub> | ||
<p> </p> | <p> </p> | ||
Revision as of 15:57, 1 August 2017
Photon Project Status Updates
Tuesday August 1, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 86% of the release goal completed.
- Team has completed 75% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 31% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 30 work items: 24 unassigned, 2 assigned and 4 completed.
Performance Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 100% of the release goal completed.
- Team has completed 83% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 26% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 128 work items: 78 unassigned, 16 assigned and 34 completed.
Structure Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 128% of the release goal completed.
- Team has completed 78% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 62% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 49 work items: 36 unassigned, 1 assigned and 12 completed.
Animation Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 100% of the release goal completed.
- Team has completed 88% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 50% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 46 work items: 21 unassigned and 7 assigned and 18 completed.
Onboarding Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 162% of the release goal completed.
- Team has completed 81% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 37% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 18 work items: 0 unassigned, 10 assigned and 8 completed.
Preference Team
- In Development.
- Team is working on Release III (July 4 - August 14) with 206% of the release goal completed.
- Team has completed 89% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 63% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 27 work items: 22 unassigned, 3 assigned and 2 completed.