Firefox/Photon/Updates: Difference between revisions
< Firefox
Jump to navigation
Jump to search
No edit summary |
No edit summary |
||
| Line 1: | Line 1: | ||
=Photon Project Status Updates= | =Photon Project Status Updates= | ||
<p> </p> | <p> </p> | ||
==Tuesday September | ==Tuesday September 19, 2017== | ||
<sub>''Note: Updated every Tuesday.''</sub> | <sub>''Note: Updated every Tuesday.''</sub> | ||
<p> </p> | <p> </p> | ||
| Line 8: | Line 8: | ||
<p> </p> | <p> </p> | ||
===Visual Redesign Team=== | ===Visual Redesign Team=== | ||
* | * MVP Completed. | ||
* Team has [http://tinyurl.com/mf4u59q completed 100%] of the Project MVP Backlog. | |||
* Team has [http://tinyurl.com/mf4u59q completed | * QA has [http://tinyurl.com/mcu9cdd verified 98%] of all Project MVP Backlog work requiring testing. | ||
* QA has [http://tinyurl.com/mcu9cdd verified | |||
<p> </p> | <p> </p> | ||
===Performance Team=== | ===Performance Team=== | ||
* | * MVP Completed. | ||
* Team has [http://tinyurl.com/k3cmwj3 completed 100%] of the Project MVP Backlog. | |||
* Team has [http://tinyurl.com/k3cmwj3 completed | * QA has [https://mzl.la/2sQiOVI verified 95%] of all Project MVP Backlog work requiring testing. | ||
* QA has [https://mzl.la/2sQiOVI verified | |||
<p> </p> | <p> </p> | ||
===Structure Team=== | ===Structure Team=== | ||
* | * MVP Completed. | ||
* Team has [http://tinyurl.com/m2gptop completed 100%] of the Project MVP Backlog. | |||
* Team has [http://tinyurl.com/m2gptop completed | * QA has [http://tinyurl.com/lytzlyk verified 98%] of all Project MVP Backlog work requiring testing. | ||
* QA has [http://tinyurl.com/lytzlyk verified | |||
<p> </p> | <p> </p> | ||
===Animation Team=== | ===Animation Team=== | ||
| Line 38: | Line 29: | ||
<p> </p> | <p> </p> | ||
===Onboarding Team=== | ===Onboarding Team=== | ||
* | * MVP Completed. | ||
* Team has [https://mzl.la/2so1BCW completed 100%] of the Project MVP Backlog. | |||
* QA has [https://mzl.la/2eMwCyH verified 95%] of all Project MVP Backlog work requiring testing. | |||
* Team has [https://mzl.la/2so1BCW completed | |||
* QA has [https://mzl.la/2eMwCyH verified | |||
<p> </p> | <p> </p> | ||
===Preference Team=== | ===Preference Team=== | ||
* In Development. | * In Development. | ||
* Team has [https://mzl.la/2wFXvHU completed 97%] of the Project MVP Backlog. | * Team has [https://mzl.la/2wFXvHU completed 97%] of the Project MVP Backlog. | ||
* QA has [https://mzl.la/2eNiDZB verified 95%] of all Project MVP Backlog work requiring testing. | |||
* QA has [https://mzl.la/2eNiDZB verified | |||
<p> </p> | <p> </p> | ||
Revision as of 13:38, 19 September 2017
Photon Project Status Updates
Tuesday September 19, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 98% of all Project MVP Backlog work requiring testing.
Performance Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 95% of all Project MVP Backlog work requiring testing.
Structure Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 98% of all Project MVP Backlog work requiring testing.
Animation Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 100% of all Project MVP Backlog work requiring testing.
- Team has completed 25 high priority reserve work items in the final release.
Onboarding Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 95% of all Project MVP Backlog work requiring testing.
Preference Team
- In Development.
- Team has completed 97% of the Project MVP Backlog.
- QA has verified 95% of all Project MVP Backlog work requiring testing.