Firefox/Activity Stream/Status/28-Nov-2016: Difference between revisions

(Created page with "__NOTOC__ <big><big><big>'''Firefox Activity Stream Program - Cross-Platform Status Report - Nov-28-2016'''</big></big></big> == Overall Project Health == File:Green-sm.jpg...")
 
 
(One intermediate revision by the same user not shown)
Line 42: Line 42:
<!--Should explain WHY for the health/status reported above.  Items covered here may be covered in more detail further down in the report.  If senior management were to look at nothing but this section, they should be able to tell what is going on with the project.-->
<!--Should explain WHY for the health/status reported above.  Items covered here may be covered in more detail further down in the report.  If senior management were to look at nothing but this section, they should be able to tell what is going on with the project.-->
===General===
===General===
* Engineering breakdown of MVP user stories is not yet complete for all platforms.  All teams are aiming to complete the breakdown exercise in the coming weeks, and once finalized a forecast for delivery of Activity Stream for each platform will be generated and communicated.  Mobile platforms are aiming to have a complete schedule by December 9th.
* Engineering breakdown of MVP user stories is not yet complete for all platforms.  All teams are aiming to complete the breakdown exercise in the coming weeks, and once finalized a forecast for delivery of Activity Stream for each platform will be generated and communicated.  Mobile platforms are aiming to have a complete schedule by December 9th - status of breakdown mobile completion can be found [https://mzl.la/2gGcEo5|here].




Line 113: Line 113:
For more details please visit the [https://trello.com/b/KX3hV8XS/activity-stream Activity Stream Trello Board]
For more details please visit the [https://trello.com/b/KX3hV8XS/activity-stream Activity Stream Trello Board]
===MVP Feature Development===
===MVP Feature Development===
*'''This section to be populated upon completion of MVP Definition.''' In the meantime please see the following for development state details:
*'''This section to be populated upon completion of MVP Definition and Breakdown.''' In the meantime please see the following for development state details:
** [https://github.com/mozilla/activity-stream/issues Desktop on GitHub]
** [https://github.com/mozilla/activity-stream/issues Desktop on GitHub]
** [https://wiki.mozilla.org/Firefox/Activity_Stream/Mobile_Sprint_Planning Mobile Sprint Planning] - work still to complete for current sprint
** [https://wiki.mozilla.org/Firefox/Activity_Stream/Mobile_Sprint_Planning Mobile Sprint Planning] - work still to complete for current sprint

Latest revision as of 16:24, 30 November 2016

Firefox Activity Stream Program - Cross-Platform Status Report - Nov-28-2016

Overall Project Health

  On track, issues well managed   Some risks, unknowns without clear mitigations   Blocked on deliverables, needs decision, escalation required

Platform/Area Version Health Notes
Desktop Add-On

 

'Okanagan Lake' sprint in progress, with end date of Dec 4th. Yellow status due to the fact that final MVP breakdown work and schedule is still pending. Shield study in progress. AS 'Graduation' planning/discussions underway.
Android FF52 TBC

 

Currently in sprint 2.0 (ending Dec 11). Currently not confirmed if 52 is the delivery vehicle as final MVP breakdown, and subsequent forecasting is still underway (hence Yellow status), targeting to complete this sprint.
iOS V7.0 TBC

 

Currently in sprint 2.0 (ending Dec 11) and V7.0 development period has begun. V7.0 as the AS delivery vehicle is not yet confirmed as final MVP breakdown, and subsequent forecasting is still underway (hence Yellow status), targeting to complete this sprint.

Exec Summary/Hot Topics

General

  • Engineering breakdown of MVP user stories is not yet complete for all platforms. All teams are aiming to complete the breakdown exercise in the coming weeks, and once finalized a forecast for delivery of Activity Stream for each platform will be generated and communicated. Mobile platforms are aiming to have a complete schedule by December 9th - status of breakdown mobile completion can be found [1].


Desktop

  • Current Sprint 'Mount Revelstoke'
  • Planning to complete MVP breakdown work in December to enable creation of MVP delivery forecast.
  • Discussions have begun on how to 'graduate' AS code to the trains, vs the current add-on, pending favorable feedback from the Shield study.

Android

  • Current Sprint 2.0
  • Priorities - finalizing breakdown, tab/home panel, highlights, telemetry.
  • Only a handful of breakdowns remain; targeting completion this week (first half of the sprint).

iOS

  • Current Sprint 2.0
  • Priorities - new tab/home panel, highlights,telemetry
  • AS feature development continues through the V7.0 development period (3 sprints ending Jan 8th).
  • Only a handful of breakdowns remain; targeting completion this week (first half of the sprint).

Risks & Issues

Description of Risk/Issue Affected Platform(s) State Owner Version Plan to Resolve/Mitigation Target Date
Final MVP definition still to be solidified All Closed Barbara/Nick TBD Product has determined which user stories are considered MVP for all platforms. Team is moving on to finalize engineering breakdown of these stories. Oct 17th
Team work capacities & therefore MVP delivery date unknown All Open Jenn TBD Dependent on final breakdown of MVP user stories. All teams somewhat delayed due to competing priorities. Mobile nearing completion, Desktop follows by a couple of weeks. Dec 24th

Development Status

  On track, issues well managed   Some risks, unknowns without clear mitigations   Blocked on deliverables, needs decision, escalation required

For more details please visit the Activity Stream Trello Board

MVP Feature Development

Feature Description Platform(s) Meta Bug Health Status

 

 

 

 

 

Important Links/References