Mobile/Firefox for iOS/Status Report/05-Aug-2016: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
No edit summary
Line 135: Line 135:
|-
|-
| Target Launch
| Target Launch
| July  
| July 27
| Complete
| Complete
|  
| Date chosen by Marketing/PM to align with promotion goals
|}
|}


== Important Links/References <!--Optional--> ==
== Important Links/References <!--Optional--> ==

Revision as of 19:00, 5 August 2016

Firefox for iOS - Program Status Report - June 28-2016

Overall Project Health

Green-sm.jpg On track, issues well managed Yellow-sm.jpg Some risks, unknowns without clear mitigations Red-sm.jpg Blocked on deliverables, needs decision, escalation required

Version Health Notes
V5.0

Green-sm.jpg

Target submission is Tuesday,July 5th.
V6.0

Green-sm.jpg

On hold until otherwise advised by senior management.

Exec Summary/Hot Topics

  • V5.0 is targeting submission on Tuesday, July 5th. Release candidate build is planned for this Thursday, but will be given the weekend to soak on Testflight.
  • Tabs for iPad was considered for uplift to V5.0, but the decision was made to hold for further testing and launch in a later release.
  • A decision has been made by senior management to continue to hold back on the release of bi-directional sync, so this feature will NOT be launching in V5.0 as initially planned.
  • Approval is expected 2-3 days post-submission. Launch timing is TBD pending Marketing/PR recommendations
  • The team will continue to monitor and triage issues, and produce bug-fix releases, which may possibly include some limited number of foundational features as approved by senior management.

Risks & Issues

Description of Risk/Issue State Owner Version Plan to Resolve/Mitigation Target Date

Cross-functional/Milestone Status

Version 5.0

Milestone/Area/Deliverable Target Date Status Notes
Feature Complete Mid-June Complete
L10N/Code Freeze Mid-June Complete
Release Candidate Build late-June Complete
App Store Submission Early - July Complete
Apple Approval ~ July 7/8 Complete
Comms/PR July 7 Complete
Marketing July 7 Complete
SUMO July 7 Complete
Legal July 7 On Track
Release Management July 7 Complete
Target Launch July 27 Complete Date chosen by Marketing/PM to align with promotion goals

Important Links/References