** Decline in average team velocity caused the Forecasted Date to Completion of Development to increase by 1 iteration from November 19 to December 05.
** Decline in average team velocity caused the Forecasted Date to Completion of Development to increase by 1 iteration from November 19 to December 05.
** Despite the decline in average team velocity, point closure increased 10% from the previous iteration.
** Despite the decline in average team velocity, point closure increased 10% from the previous iteration.
<p> </p>
* '''Release Highlights'''
* '''Release Highlights'''
** At the conclusion of Iteration #9, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75, the Metro Team has a median velocity of 51 and there is a 90% likelihood that the actual velocity will fall between 32 and 74.
** At the conclusion of Iteration #9, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75, the Metro Team has a median velocity of 51 and there is a 90% likelihood that the actual velocity will fall between 32 and 74.
Line 31: Line 32:
*** '''Expected Release Scenario''' - With a velocity performance of 51 development would be completed in 11 iterations on December 05, 2013.  
*** '''Expected Release Scenario''' - With a velocity performance of 51 development would be completed in 11 iterations on December 05, 2013.  
*** '''Optimistic Release Scenario''' - With a velocity performance of 74 development would be completed no later than 8 iterations on October 22, 2013.   
*** '''Optimistic Release Scenario''' - With a velocity performance of 74 development would be completed no later than 8 iterations on October 22, 2013.   
<p> </p>
* '''Quality Highlights'''
* '''Quality Highlights'''
** The quality performance from the regression testing across Iterations #1 - #8 is as follows:
** The quality performance from the regression testing across Iterations #1 - #8 is as follows:
Line 36: Line 38:
*** 10% fail rate.
*** 10% fail rate.
*** 88% test coverage.
*** 88% test coverage.
<p> </p>
* '''Feature Completeness Highlights'''
* '''Feature Completeness Highlights'''
** At the conclusion of Iteration #9, 44% of Feature Stories are Incomplete - development finished in a previous iteration but contain blocking defects and/or change requests.