** Despite the decline in average team velocity, point closure increased 10% from the previous iteration. | ** Despite the decline in average team velocity, point closure increased 10% from the previous iteration. | ||
* '''Release Highlights''' | * '''Release Highlights''' | ||
** | ** At the conclusion of Iteration #9, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75, the Metro Team has a median velocity of 51 and there is a 90% likelihood that the actual velocity will fall between 32 and 74. | ||
*** Pessimistic Release Scenario - With a velocity performance of 32 development would be completed no earlier than 17 iterations on March 06, 2014. | *** '''Pessimistic Release Scenario''' - With a velocity performance of 32 development would be completed no earlier than 17 iterations on March 06, 2014. | ||
*** | *** '''Expected Release Scenario''' - With a velocity performance of 51 development would be completed in 11 iterations on December 05, 2013. | ||
*** | *** '''Optimistic Release Scenario''' - With a velocity performance of 74 development would be completed no later than 8 iterations on October 22, 2013. | ||
* '''Quality Highlights''' | * '''Quality Highlights''' | ||
** The quality performance from the regression testing across Iterations #1 - #8 is as follows: | ** The quality performance from the regression testing across Iterations #1 - #8 is as follows: | ||