Unified Telemetry/Status reports/EventTelemetry/Oct 28 2016: Difference between revisions

From MozillaWiki
Jump to navigation Jump to search
(infos)
 
(→‎Exec Summary: updates)
 
Line 9: Line 9:


=== Exec Summary ===
=== Exec Summary ===
* Project in Green (no known blockers). Go live spread over 52 and 53. Targets are Activity stream and Synch.
* Go live spread over 52 and 53. Next targets are Activity stream and Synch.
* Met with AS to discuss road map and when they engage on EventTelemetry  
* Met with AS to discuss road map and when they engage on EventTelemetry  
** Marina and Georg to begin co-working
** validation and POC next, pipeline work TBD
** POC/Validation in Q4
* Synch engagement next week
* Synch


=== Risks/Issues ===
=== Risks/Issues ===

Latest revision as of 16:45, 28 October 2016

[previous weeks report]

Event Telemetry status report October 28, 2016

Overall Project Health

Last week: Green

This week: Green

Exec Summary

  • Go live spread over 52 and 53. Next targets are Activity stream and Synch.
  • Met with AS to discuss road map and when they engage on EventTelemetry
    • validation and POC next, pipeline work TBD
  • Synch engagement next week

Risks/Issues

Description of Risks/Issues State Owner Plan to Resolve/Mitigation Target Date
Get sign off on proposal done Georg sign offs required from TestPilot (Will Clouser), Ilana, RobFromBRC, John Dorlus, done
Notify Org post signoff done Thomas/Georg Notify FX-Team, UITour stakholders, Jared, Mike Connoly done
Assess what event measurements in Activity Stream can be measured via the Event Telemetry approach done Ilana Investigate done
Escalate request for UX feedback to Product and Data leadership In process Katie Escalation In flight
event registry integration in add-ons Done Georg seek consensus Done

Accomplished for Last Period

  • Will completed event draft
  • Conversation with AS started (notes)


Planned for Next Period

  • Georg and Marina to begin work
  • POC / Validation work
  • Current QA effort evaluation and next steps

Proposed development stages and status

Stage State description Target Date
Proposal creation Done accepted August 1, 2016
Kick off Done RACI + develpoment stages August 14, 2016
Development to allow test pilot to begin using and submitting TBD ingestion, storage, make available for analysis TBD
QA Validation TBD Test to validate UITelemtry TBD
Processing TBD TBD TBD
Tooling TBD TBD TBD

Probe / Event dependancies and timeline

Name of probe design and review Use cases / questions list of events & priorities for implementation who implements and owns the probe who owns analysis
Activity Stream Events design use cases event list implement and own analysis owner
UItelemetry Events design use cases event list implement and own analysis owner
Search events design use cases event list implement and own analysis owner
Engagement measures events design use cases event list implement and own analysis owner
Test pilot events design use cases event list implement and own analysis owner
Mobile Telemetry design use cases event list implement and own analysis owner

Important Links/References