Items for consideration (time estimates to come) that should be completed by late February  
Items for consideration (time estimates to come) that should be completed by late February  


'''Format: '''['''due date] '''task''' ('''comment''')
'''Format: '''['''due date''']<span style="font-weight: bold;"> </span>'''task''' ('''comment''')  


*[22/11/10] The sites core functionality (ie. the bare minimum)<br>
*[22/11/10] The sites core functionality (ie. the bare minimum)<br>  
*[29/11/10] The domain name structure (recommended:&nbsp;[[Websites/Taskforce/Proposals/Domain_Name_Strategy|following Mozilla]] on this one)<br>
*[29/11/10] The domain name structure (recommended:&nbsp;[[Websites/Taskforce/Proposals/Domain Name Strategy|following Mozilla]] on this one)<br>  
*[13/12/10] The content overhaul and creation (already started)
*[13/12/10] The content overhaul and creation (already started)  
*[03/01/11] Theme tweaks (not redesign, just minor tweaks)
*[03/01/11] Theme tweaks (not redesign, just minor tweaks)  
*[10/01/11] Site downtime (a maintainance page should also be created for this task)
*[10/01/11] Site downtime (a maintainance page should also be created for this task)  
*[24/01/11] Impliment changes (all of them, not just some)
*[24/01/11] Impliment changes (all of them, not just some)  
*[31/01/11] Relaunch site! (Yay!)
*[31/01/11] Relaunch site! (Yay!)  
*[02/11] Face-to-face meetup to work out long term plan (Double yay!)
*[02/11] Face-to-face meetup to work out long term plan (Double yay!)


 
<br>


The plan for completing these should follow loosely with the unix philosophy of doing one thing and doing it well. So we should do one task, do it well, then move to the next while taking the results of the previous into account.
The plan for completing these should follow loosely with the unix philosophy of doing one thing and doing it well. So we should do one task, do it well, then move to the next while taking the results of the previous into account.

Revision as of 18:37, 16 November 2010

What is The Mozilla UK Community Portal?

The Mozilla UK community portal was designed to bring the UK community together in a central place. Feel free to post feed back in our forums and get involved!

You can also visit the beta version of the site by visiting www.mozilla-uk.org

Community Roadmap

The Revamp

Items for consideration (time estimates to come) that should be completed by late February

Format: [due date] task (comment)

  • [22/11/10] The sites core functionality (ie. the bare minimum)
  • [29/11/10] The domain name structure (recommended: following Mozilla on this one)
  • [13/12/10] The content overhaul and creation (already started)
  • [03/01/11] Theme tweaks (not redesign, just minor tweaks)
  • [10/01/11] Site downtime (a maintainance page should also be created for this task)
  • [24/01/11] Impliment changes (all of them, not just some)
  • [31/01/11] Relaunch site! (Yay!)
  • [02/11] Face-to-face meetup to work out long term plan (Double yay!)