(Created page with "= Overall = * Audit toolchain of web apps on the critical path to ship Firefox. (laura) For each: ** Bug audit and triage ** Safety check: monitoring, redundancy, backups, etc *...") |
|||
Line 9: | Line 9: | ||
= Socorro = | = Socorro = | ||
* Crashkill priority bug list [ | * Crashkill priority bug list [https://wiki.mozilla.org/CrashKill/Plan/Priorities#Proposal_-_Q1.2F2012 priority ordering] [https://bugzilla.mozilla.org/buglist.cgi?classification=Server%20Software&status_whiteboard_type=allwordssubstr&query_format=advanced&status_whiteboard=Q12012wanted&component=Socorro&product=Webtools&list_id=1962280 bugs] (lonnen, sneethling, brandonsavage, adrian) | ||
* json changes (lars) [CARRYOVER] | * json changes (lars) [CARRYOVER] | ||
* Move remaining SQL access into middleware (adrian) | * Move remaining SQL access into middleware (adrian) |
Revision as of 15:52, 28 December 2011
Overall
- Audit toolchain of web apps on the critical path to ship Firefox. (laura)
For each:
- Bug audit and triage
- Safety check: monitoring, redundancy, backups, etc
- Documentation check
- Find or assign owner
- Future plan, depending on the above
Socorro
- Crashkill priority bug list priority ordering bugs (lonnen, sneethling, brandonsavage, adrian)
- json changes (lars) [CARRYOVER]
- Move remaining SQL access into middleware (adrian)
- PoC with queue (rhelmer)
- Get ElasticSearch into production (adrian)
- Integrate configman into Socorro (lars, peterbe)
- Investigate multi-homing (rhelmer)
Graphs
- (with RelEng) Update graph server to support RelEng changes to make Talos more statistically reliable (rhelmer)
Elmo
- Complete new design and homepage (peterbe)
- Deploy on new infrastructure - with IT (peterbe, shyam, laura)
- Complete move to l10n.mozilla.org - with IT (peterbe, shyam, laura)
- Add Webtrends metrics (laura)
- Launch! (all)
- Spec out drain app (laura)
RelEng dashboard
- Build a monitoring and capacity planning dashboard for the build farm (with RelEng, IT)
mxr/dxr
- Triage mxr bugs, fix outstanding blockers/critical bugs (laura, rhelmer)
- Complete handover from Taras' team on backend completion (end Feb?) (?)
- Develop a plan for switchover (laura, rhelmer)
Other
- Support Pontoon team through deployment on real infrastructure (laura, peterbe)
- Deploy new PTO app on real infrastructure (laura, peterbe)