Agenda

  • New PM - Chris Peterson
  • Summit update (Lawrence)
  • Tribe sessions
  • Meeting next week
  • Headcount update
  • Stability work week (Aug 19-23 MV)
  • FHR update

Candice

  • FFOS Agile rollout update
  • Work weeks - functional teams in progress
  • Next steps (Candice, Martin, Marco, Sheila)

Dietrich

  • Open Source Bridge this week, Firefox OS hacking event tonight
  • LG QE3 workweek in Taipei June 24 - 28
  • LG QE3 ending this week, up to 73 bugs right now

Erin

  • Roadmap management
  • Fx22 GA readiness
  • Shumway
  • WebRTC (ramping up)
  • Dynamic Snippets (risk management)

Lawrence

  • Summit planning assembly
  • Performance project planning for front-end teams
  • Mobile Web compat hiring

Martin

Michael

  • PTO this week
  • Taipei Jul 1-3

Marco

  • Team working on Iteration #9 - June 12, 2013 - June 25, 2013
  • QA working on testing IT #0 - IT #8 - 18 bugs remain to be tested.
  • Metro Test Day scheduled for Friday June 28.

Sheila

  • Still more interviews for Payments PM
  • FFOS
    • 1.2 scoping - working with Faramarz/Chris Lee on getting "gut checks" for feature list
    • Helping with roll-out plan - documentation, meetings, presentations
    • Working with Larissa on updates for weekly sponsors meetings
  • FHR
    • Working with John Jensen on transitioning meetings

Tauni

  • focused on leveling resources this week
  • PTO July 22 - 26