Betafarm/Weekly-Status-Reports/2012-05-08
< Betafarm
Jump to navigation
Jump to search
Summary
| DOC VERSION: 1.0 | STATUS REPORT AS OF: May 8 2012 |
| AUTHOR: Benjamin Sternthal |
| TPM: Benjamin Sternthal |
| PROJECT SPONSOR: David Ascher |
| PROJECT WIKI: Betafarm |
Status
| 1. STATUS | |||||
| Status Item | On Track | Caution | Crisis | N/A | Comment |
| OVERALL STATUS | X | ||||
| Schedule | X | ||||
| Scope | X | ||||
| Budget | X | ||||
Schedule & Budget
| 2. SCHEDULE | |||
| Start Date | Completion Date | ||
| Original | Current | Original | Current |
| April 18 | April 18 | May 9 | May 9 |
| 3. BUDGET | |||
| Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
| N/A | N/A | N/A | N/A |
Recent Accomplishments
| 4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
| 5. UPCOMING TASKS | ||||
| Task | Owner | Due Date | Bugzilla | Comments |
| -- | ||||
Major Issues
| 6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
| Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
| -- | |||||||
Project Milestones
| 7. PROJECT MILESTONES | |||||||
| Issue | Owner | Target Completion Date |
Revised Completion Date |
Actual Completion Date |
Bugzilla | Status | |
| WebDev | |||||||
| Release 1.1 Ready To Test | PM | 5/1 | Complete | ||||
| Release 1.1 Live | PM/IT | 5/9 | Complete | ||||
| Privacy | |||||||
| Privacy Review | N/A | ||||||
| QA | |||||||
| QA Review | RB | 4/30 - 5/8 | 747223 | Complete | |||
| Security | |||||||
| Security Review | MG | N/A | |||||
| IT | |||||||
| Prod Deployment | BB | 5/9 | Complete | ||||