Photon Project Status Updates
Tuesday, May 23, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is at the start of Release II (May 23 - July 3) with 0% of the release goal completed.
- Team has completed 37% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 15% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 7 lower-priority work items with 1 completed.
Performance Team
- In Development.
- Team is at the start of Release II (May 23 - July 3) with 0% of the release goal completed.
- Team has completed 55% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 14% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 115 lower-priority work items with 9 currently in development.
Structure Team
- In Development.
- Team is at the start of Release II (May 23 - July 3) with 5% of the release goal completed.
- Team has completed 38% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 26% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 10 lower-priority work items.
Animation Team
- In Development.
- Team is at the start of Release II (May 23 - July 3) with 0% of the release goal completed.
- Team has completed 33% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 14% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 12 lower-priority work items with 1 currently in development.
Onboarding Team
- In Development.
- Release 55 to date - view work.
- Project Backlog to date - view work.
- Completion to date - view work.
- First and second releases will be used to gather performance data in order to set the MVP release forecast.
- Release forecast and MVP Backlog to be set on Tuesday July 4.
Preference Team
- In Development.
- Team is at the start of Release II (May 23 - July 3) with 0% of the release goal completed.
- Team has completed 33% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 18% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 16 lower-priority work items with 1 currently in development.