Photon Project Status Updates
Tuesday June 06, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is working on Release II (May 23 - July 3) with 59% of the release goal completed.
- Team has completed 52% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 21% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 12 work items: 8 unassigned, 1 assigned and 3 completed.
Performance Team
- In Development.
- Team is working on Release II (May 23 - July 3) with 50% of the release goal completed.
- Team has completed 63% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 9% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 118 work items: 101 unassigned, 9 assigned and 8 completed.
Structure Team
- In Development.
- Team is working on Release II (May 23 - July 3) with 100% of the release goal completed.
- Team has completed 65% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 32% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 19 work items: 14 unassigned, 0 assigned and 5 completed.
Animation Team
- In Development.
- Team is working on Release II (May 23 - July 3) with 100% of the release goal completed.
- Team has completed 40% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 14% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 12 work items: 11 unassigned and 1 assigned and 0 completed.
Onboarding Team
- In Development.
- Release 55 to date - view work.
- Project Backlog to date - view work.
- Completion to date - view work.
- First and second releases will be used to gather performance data in order to set the MVP release forecast.
- Release forecast and MVP Backlog to be set on Tuesday July 4.
Preference Team
- In Development.
- Team is working on Release II (May 23 - July 3) with 100% of the release goal completed.
- Team has completed 64% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 32% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog contains 15 work items: 15 unassigned, 0 assigned and 0 completed.