Photon Project Status Updates
Tuesday August 15, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 10% of the release goal completed.
- Team has completed 95% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 50% of all Project MVP Backlog work requiring testing.
- Team's goal is to complete 15 high priority reserve work items in the final release.
Performance Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 0% of the release goal completed.
- Team has completed 91% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 47% of all Project MVP Backlog work requiring testing.
- Team has no plans to complete high priority reserve work items in the final release.
Structure Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 13% of the release goal completed.
- Team has completed 90% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 74% of all Project MVP Backlog work requiring testing.
- Team's goal is to complete 4 high priority reserve work items in the final release.
Animation Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 91% of all Project MVP Backlog work requiring testing.
- Team's goal is to complete 6 high priority reserve work items in the final release.
Onboarding Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 25% of the release goal completed.
- Team has completed 96% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 78% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog update will be made available on Friday August 18.
Preference Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 0% of the release goal completed.
- Team has completed 92% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 63% of all Project MVP Backlog work requiring testing.
- Project Reserve Backlog update will be made available on Friday August 18.