Photon Project Status Updates
Tuesday August 22, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 73% of the release goal completed.
- Team has completed 99% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 75% of all Project MVP Backlog work requiring testing.
- Team has completed 16 high priority reserve work items in the final release.
Performance Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 13% of the release goal completed.
- Team has completed 92% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 45% of all Project MVP Backlog work requiring testing.
- Team has no plans to complete high priority reserve work items in the final release.
Structure Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 40% of the release goal completed.
- Team has completed 94% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 82% of all Project MVP Backlog work requiring testing.
- Team has completed 8 high priority reserve work items in the final release.
Animation Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 84% of all Project MVP Backlog work requiring testing.
- Team has completed 7 high priority reserve work items in the final release.
Onboarding Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 55% of the release goal completed.
- Team has completed 94% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 81% of all Project MVP Backlog work requiring testing.
- Team has completed 5 high priority reserve work items in the final release.
Preference Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 68% of the release goal completed.
- Team has completed 95% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 70% of all Project MVP Backlog work requiring testing.
- Team has completed 0 high priority reserve work items in the final release.