Photon Project Status Updates
Tuesday September 05, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 82% of the release goal completed.
- Team has completed 99% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 81% of all Project MVP Backlog work requiring testing.
- Team has completed 28 high priority reserve work items in the final release.
Performance Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 63% of the release goal completed.
- Team has completed 97% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 63% of all Project MVP Backlog work requiring testing.
- Team has no plans to complete high priority reserve work items in the final release.
Structure Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 71% of the release goal completed.
- Team has completed 97% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 86% of all Project MVP Backlog work requiring testing.
- Team has completed 22 high priority reserve work items in the final release.
Animation Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 100% of all Project MVP Backlog work requiring testing.
- Team has completed 19 high priority reserve work items in the final release.
Onboarding Team
- In Development.
- Last minute scope change happened on 8/22 creating 12 more new MVP bugs.
- Team is working on Release IV (August 15 - September 15) with 61% of the release goal completed.
- Team has completed 89% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 80% of all Project MVP Backlog work requiring testing.
- Team has completed 6 high priority reserve work items in the final release.
Preference Team
- In Development.
- Team is working on Release IV (August 15 - September 15) with 88% of the release goal completed.
- Team has completed 98% of the Project MVP Backlog.
- On track for completion of the Project MVP Backlog for Release 57.
- QA has verified 78% of all Project MVP Backlog work requiring testing.
- Team has completed 0 high priority reserve work items in the final release.