Photon Project Status Updates

Tuesday September 05, 2017

Note: Updated every Tuesday.

Project Tracking

Visual Redesign Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 82% of the release goal completed.
  • Team has completed 99% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 85% of all Project MVP Backlog work requiring testing.
  • Team has completed 34 high priority reserve work items in the final release.

Performance Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 88% of the release goal completed.
  • Team has completed 99% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 80% of all Project MVP Backlog work requiring testing.
  • Team has no plans to complete high priority reserve work items in the final release.

Structure Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 86% of the release goal completed.
  • Team has completed 99% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 97% of all Project MVP Backlog work requiring testing.
  • Team has completed 32 high priority reserve work items in the final release.

Animation Team

  • MVP Completed.
  • Team has completed 100% of the Project MVP Backlog.
  • QA has verified 100% of all Project MVP Backlog work requiring testing.
  • Team has completed 25 high priority reserve work items in the final release.

Onboarding Team

  • In Development.
  • Last minute scope change happened on 8/22 creating 12 more new MVP bugs.
  • Team is working on Release IV (August 15 - September 15) with 88% of the release goal completed.
  • Team has completed 97% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 93% of all Project MVP Backlog work requiring testing.
  • Team has completed 9 high priority reserve work items in the final release.

Preference Team

  • In Development.
  • Team is working on Release IV (August 15 - September 15) with 87% of the release goal completed.
  • Team has completed 97% of the Project MVP Backlog.
  • On track for completion of the Project MVP Backlog for Release 57.
  • QA has verified 92% of all Project MVP Backlog work requiring testing.
  • Team has completed 0 high priority reserve work items in the final release.