Photon Project Status Updates
Tuesday September 19, 2017
Note: Updated every Tuesday.
Project Tracking
Visual Redesign Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 98% of all Project MVP Backlog work requiring testing.
Performance Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 95% of all Project MVP Backlog work requiring testing.
Structure Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 98% of all Project MVP Backlog work requiring testing.
Animation Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 100% of all Project MVP Backlog work requiring testing.
- Team has completed 25 high priority reserve work items in the final release.
Onboarding Team
- MVP Completed.
- Team has completed 100% of the Project MVP Backlog.
- QA has verified 95% of all Project MVP Backlog work requiring testing.
Preference Team
- In Development.
- Team has completed 97% of the Project MVP Backlog.
- QA has verified 95% of all Project MVP Backlog work requiring testing.