Program Management/Weekly-Status-Reports/2012-06-26
Meeting Topics
- Mobile baby, yeah! \o/
- Basecamp
Dietrich
- PTO - until July 2nd.
Erin
• I may or may not make this; will be here at 5:00AM MTV • Mobile release risk management/mitigation • Intensive beta review and mining of data on Google Play • Constant review of new bugs/new noms • Fulfilling product requests • Bug 764518 - Fennec Native Go Live: Be sure blocked devices are properly filtered <== drove effort to scrub to find specs for almost 700 devices • Obtained sign-off from cross-functional teams and drove GA Readiness Review & follow ups (in-person legal review/sign off, & server ops sign off) • Starting on Post-Mortem
Lawrence
- Basecamp
- Working with GFX/Layout and WebAPI teams to define scope/work, identify dependencies, and draft schedule.
- Kilimanjaro
- Triage seems to be primarily focused around Apps, Marketplace, and AItC, with some Identity. Not surprising as B2G is handled as part of basecamp triage and there aren't a lot of requirements on desktop and mobile outside of Apps.
- Mobile Web Compat
- Lots of meeting attendance but little resource to do leg work. Need to engage broader Mozilla community.
- Silent update
- Background Updates preffed on for Windows on Aurora. \o/
- Snappy
- Moving more slowly as resource have been pulled for various other priorities. Working on resource contention issues.