Summary
| DOC VERSION: 1.0 | STATUS REPORT AS OF: Feb 28 2012 |
| AUTHOR: Benjamin Sternthal |
| TPM: Benjamin Sternthal |
| PROJECT SPONSOR: David Ascher |
| PROJECT WIKI: Betafarm |
Status
| 1. STATUS | |||||
| Status Item | On Track | Caution | Crisis | N/A | Comment |
| OVERALL STATUS | X | ||||
| Schedule | X | ||||
| Scope | X | ||||
| Budget | X | ||||
Schedule & Budget
| 2. SCHEDULE | |||
| Start Date | Completion Date | ||
| Original | Current | Original | Current |
| Jan 17 | Jan 17 | March 30 | N/A |
| 3. BUDGET | |||
| Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
| N/A | N/A | N/A | N/A |
Recent Accomplishments
| 4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
| 5. UPCOMING TASKS | ||||
| Task | Owner | Due Date | Bugzilla | Comments |
| Define Scope Q1 Release | DA/BS | 2012-02-20 | --- | Complete |
| Create IT Bugs/Dev/Stage/Figure Out Production | BS /PM | 2012-02-30 | --- | In Progress |
| Schedule Sign Off By Teams | BS/Teams | 2012-02-30 | --- | Complete |
Major Issues
| 6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
| Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
| HP Design | DA | High | 2012-03-07 | 728410 | |||
| Decide on Branding & Domain Name | DA | High | 2012-03-01 | -- | Complete | ||
Project Milestones
| 7. PROJECT MILESTONES | |||||||
| Issue | Owner | Target Completion Date |
Revised Completion Date |
Actual Completion Date |
Bugzilla | Status | |
| WebDev | |||||||
| Release 1 Ready To Test | PM/Tofu | 3/16 | |||||
| Release 1 Live | PM/Tofu | 3/30 | |||||
| Content | |||||||
| Content Import | PM/HH | 3/16 | |||||
| Content Entry | HH | 3/19 - 3/23 | |||||
| Privacy | |||||||
| Privacy Review | AH | 3/19 - 3/23 | 728334 | ||||
| QA | |||||||
| QA Review | RB | 3/19 - 3/23 | 728464 | ||||
| Security | |||||||
| Security Review | MG | 3/26 - 3/28 | 718891 | ||||
| IT | |||||||
| BB | |||||||