Churn V2 status report August 21, 2015

Overall Project Health

Last week: Green

This week: Green

Exec Summary

  • Work begins to deliver first milestone (reporting dashboards for v1 churn)
    • meet on Monday to define a week and cohort definitions
    • estimate effort and begin work

Risks/Issues

Description of Risks/Issues State Owner Plan to Resolve/Mitigation Target Date
Internal and external reviewers for milestones deliverables Done Thomas/John generate the list 8/19
Break work into user stories In progress Thomas/John create user stories 8/24
Investigate growth team overlaps In progress Rebecca meeting with CMore 8/24
Create milestones and project plan In progress Thomas align with 2 weeks iterations on FF 8/24
Meet with stakeholders to identify key metrics to be displayed Meet monday 24th Team meeting with CMore, Max, Michael Han 8/24
Define cohorts and what a week is in progress JJ, Cmore, Max to be defined on monday aug 24 8/24

Accomplished for Last Period

  • Agreed on first milestone (end of Q3), set up meetings with key stakeholders
  • Churn V2 proposal sign off by Cmore and Eric Petit

Planned for Upcoming Period

  • Meet with stakeholders to identify on metrics to be displayed (monday)
  • Mock up visualization
  • Create filters to select dimensions
  • Need to understand if .csv files are adequate, or if we need a dashboard

Outstanding requests not yet road mapped into a release

TBD