Churn V2 status report July 31, 2015
Overall Project Health
Last week: Green
This week: Green
Exec Summary
- Roles and deliverables understood. Sign off on proposal, then creating schedule and breaking work into deliverables aligned with milestones is next
Risks/Issues
Description of Risks/Issues | State | Owner | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|
Internal and external reviewers for milestones deliverables | In progress | Thomas/John | generate the list | 8/10 |
Break work into user stories | In progress | Thomas/John | create user stories | 8/10 |
Investigate growth team overlaps | In progress | Rebecca | meeting with CMore | 8/10 |
Create milestones and project plan | In progress | Thomas | align with 2 weeks iterations on FF | 8/10 |
Accomplished for Last Period
- Agreed on using firefox iterations as milestones, next 4 are: 42.3 - august 10th, 43.1 - august 24th, 43.2 - sept 7th, 43.3 - sept 21.
- Meeting cadence, next steps agreed on
Planned for Upcoming Period
- Initial deliverable (Reporting dashboards for V1 Churn) to be broken into user stories and sheduled against milestones
- Proposal sign off (make sure we have the correct audience to get sign off)
- Meeting with CMore/Growth - narrative regarding differences between growth and churn projects
Outstanding requests not yet road mapped into a release
TBD