Overall Project Health

Last week: Green

This week: Green

Exec Summary

  • Roles and deliverables understood. Sign off on proposal, then creating schedule and breaking work into deliverables aligned with milestones is next

Risks/Issues

Description of Risks/Issues State Owner Plan to Resolve/Mitigation Target Date
Internal and external reviewers for milestones deliverables In progress Thomas/John generate the list 8/10
Break work into user stories In progress Thomas/John create user stories 8/10
Investigate growth team overlaps In progress Rebecca meeting with CMore 8/10
Create milestones and project plan In progress Thomas align with 2 weeks iterations on FF 8/10

Accomplished for Last Period

  • Agreed on using firefox iterations as milestones, next 4 are: 42.3 - august 10th, 43.1 - august 24th, 43.2 - sept 7th, 43.3 - sept 21.
  • Meeting cadence, next steps agreed on

Planned for Upcoming Period

  • Initial deliverable (Reporting dashboards for V1 Churn) to be broken into user stories and sheduled against milestones
  • Proposal sign off (make sure we have the correct audience to get sign off)
  • Meeting with CMore/Growth - narrative regarding differences between growth and churn projects

Outstanding requests not yet road mapped into a release

TBD