Kick off meeting to build big picture context and identify interim milestones occurred on July 8th 1
Meeting with Platform Security and Services to enumerate dependencies for TP is happening on July 9th.
Dependencies on Platform Sec and Services teams push this program to 'yellow'. Once we have the work required from them defined and estimated, we may go to green.
Other product deliverables for November 3rd launch are being defined (iOS Android, DevEdition).
Cultivating plan from the FxOS team so that we may ensure full transparency as we plan out launch day
Next milestones include a Campaign Plan (including umbrella brief from marketing + engagement) and a kick off meeting next week
Issues & Risks
Risk
State
Owner
Mitigation Plan
Target Date
Project Plan for Overall Campaign
Open
Erin
July 6
Accomplished for the Last Period
Desktop Planning is finalized and work is underway
'Durable' team met in Whistler and decided upon creating a Campaign Umbrella Brief - need to identify hand off date
Planned for Last Period but Not Accomplished
None
Planned for the Upcoming Period
Campaign Plan (overall story for the campaign with details, milestones, dates)
Campaign Umbrella Brief (handoff from marketing and engagement)