Firefox/Metro/Iteration11StatusReport
From MozillaWiki
Contents
Iteration #11 Status Report
Overall Project Performance
- From Iterations #1 - #11:
- Total Project Story Points: 1,004
- Story Points Completed: 624
- Story Points Remaining to Completion: 380
- Team Velocity: 63 Per Iteration
- Iterations Remaining to Completion: 7
- Forecasted Date to Completion of Development: November 11, 2013
- Total Stories Closed: 203
- Percentage of Work Completed: 62%
- Current Backlog Status:
- Story Backlog: 28 feature stories ready for development in upcoming iterations.
- Defect & Change Backlog: 34 defect and change stories ready for development in upcoming iterations.
- Planning Backlog: 16 stories for the Product Manager to review and edit for inclusion in the Story Backlog.
Iteration #11 Performance
- Performance Highlights
- Team completed 77 story points across 34 features which resulted in an increased average team velocity of 63 story points per iteration.
- Average team velocity rate increased 10% from the previous iteration.
- Increase in average team velocity caused two reductions in the schedule forecast:
- the Expected Forecasted Date to Completion of Development contracted by 1 iteration to November 11.
- the Pessimistic Forecasted Date to Completion of Development contracted by 1 iteration to February 11.
- Point closure increased 2% from the previous iteration.
- Release Highlights
- At the conclusion of Iteration #11, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75,75,77, the Metro Team has a median velocity of 63 and there is a 90% likelihood that the actual velocity will fall between 33 and 75.
- Pessimistic Development Complete Scenario - With a velocity performance of 33 development would be completed no earlier than 13 iterations on February 11, 2014 - Development Iteration #24.
- Expected Development Complete Scenario - With a velocity performance of 63 development would be completed in 7 iterations on November 11, 2013 - Development Iteration #18.
- Optimistic Development Complete Scenario - With a velocity performance of 75 development would be completed no later than 6 iterations on October 28, 2013 - Development Iteration #17.
- At the conclusion of Iteration #11, given the historical velocity performance values of 30,32,33,46,51,63,68,74,75,75,77, the Metro Team has a median velocity of 63 and there is a 90% likelihood that the actual velocity will fall between 33 and 75.
- Quality Highlights
- The quality performance from the regression testing across Iterations #1 - #10 is as follows:
- 92% pass rate - a 4% increase from the previous iteration.
- 8% fail rate - a 33% reduction from the previous iteration.
- 100% test coverage.
- The quality performance from the regression testing across Iterations #1 - #10 is as follows:
- Feature Completeness Highlights
- At the conclusion of Iteration #10, 17% of Feature Stories are Incomplete - development finished in a previous iteration but contain blocking defects and/or change requests.
- 3% of the current Defect & Change Backlog has yet to be related to a completed Feature Story.
35 Total; 0 Open (0%); 11 Resolved (31.43%); 24 Verified (68.57%);
Iteration Performance History
Iteration #1: View Backlog
- Story Points Completed = 30
- Stories Completed = 5
- Team Velocity: 30 Per Iteration
Iteration #2: View Backlog
- Story Points Completed = 32
- Stories Completed = 6
- Team Velocity: 32 Per Iteration
Iteration #3: View Backlog
- Story Points Completed = 33
- Stories Completed = 10
- Team Velocity: 32 Per Iteration
Iteration #4: View Backlog
- Story Points Completed = 63
- Stories Completed = 14
- Team Velocity: 40 Per Iteration
Iteration #5: View Backlog
- Story Points Completed = 75
- Stories Completed = 25
- Team Velocity: 47 Per Iteration
Iteration #6: View Backlog
- Points Completed: 74
- Stories Completed: 20
- Team Velocity: 51 Per Iteration
Iteration #7: View Backlog
- Points Completed: 68
- Stories Completed: 23
- Team Velocity: 54 Per Iteration
Iteration #8: View Backlog
- Points Completed: 46
- Stories Completed: 21
- Team Velocity: 53 Per Iteration
Iteration #9: View Backlog
- Points Completed: 51
- Stories Completed: 15
- Team Velocity: 51 Per Iteration
Iteration #10: View Backlog
- Points Completed: 75
- Stories Completed: 30
- Team Velocity: 57 Per Iteration
Iteration #11: View Backlog
- Points Completed: 77
- Stories Completed: 34
- Team Velocity: 63 Per Iteration
Upcoming Iteration
- Iteration #12: July 29, 2013 - August 12, 2013
- View Sprint Backlog